1969 Case No. 31 of 2024
Inland Power Limited (IPL) Vrs. JBVNL & Ors
Approval of Capital Cost for installation of bed ash handling and conveying system with construction of dry ash dumping pond for 1*63 MW Coal Fired CFBC Thermal Power Project 25.10.2024
1968 Case No. 30 of 2024
Inland Power Limited (IPL)
Review of order dated 22.07.2024 w.r.t True-up for FY 2022-23 25.10.2024
1967 Case No. 29 of 2024
M/s Eastern Coalfields Limited Vrs. Jharkhand Urja Sancharan Nigam Limited & Ors
For direction upon the Respondent JUSNL to release the claim amount of Rs.32.97 Cr. which is the 80% of the operations & Maintenance (O&M) cost borned by the petitioner upto April 2015 25.10.2024
1966 Case No. 21 of 2024
M/s Tata Power Company Limited Vrs. Tata Steel Limited (TSL)
Review of order dated 06.06.2024 passed by JSERC in Case (T) No. 11of 2023 for true-up for the FY 2022-23 and APR for FY 2023-24 with respect to unit 2 & 3 (2x120 MW) of Jojobera Power Plant of Tata Power Company Limited (TPCL) 25.10.2024
1965 Case No. 19 of 2024
M/s Royal Instrument India Pvt. Ltd. Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Seeking necessary approval to take H.T. Connection on 33 KV line from JBVNL having contract demand of 450 KVA. 25.10.2024
1964 Case No. 14 of 2024
Inland Power Limited (IPL)
Review of order dated 26.02.2024 regarding True-up for FY 2021-22 25.10.2024
1963 Case No 10 of 2024
Amalgam Steel & Power Limited (ASPL) Vrs. JREDA
For seeking direction that the Captive Power Plant of the petitioner be treated as co-generation power plant and also for relaxation/exemption in compliance of RPO on total installed capacity of 30 MW, since 15 MW out of 30 MW Capacity Generation of Power by Petitioner Company is generated thorugh its waste heat recovery boiler (WHRB) 25.10.2024
1962 Case No. 09 of 2024
Amalgam Steel & Power Limited (ASPL) Vrs. JREDA
For seekingdirection that the Captive Power Plant of the petitioner be treated as co-generation power plant and also for relaxation/exemption in compliance of RPO on total installed capacity of 30 MW, since 15 MW out of 30 MW Capacity Generation of Power by Petitioner Company is generated thorugh its waste heat recovery boiler (WHRB) from/for the year 2019-20 and 2020-21. 25.10.2024
1961 Case No. 08 of 2024
M/s Grasim Industry Limited Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Non-compliance of the order/direction dated 16.05.2023 passed by this Commission in Case No. 26 of 2020 25.10.2024
1960 Case No. 03 of 2024
Tata Steel Limited (TSL)
Review of the order dated 31.10.2023 passed in Case No. 30 of 2020 25.10.2024
1959 Case No. 17 of 2022
 Inland Power Limited (IPL) Vrs. JUVNL & Ors
Review of order dated 04th November 2022 for True up for FY 2019-20 25.10.2024
1958 Case No.12 of 2019 (Tariff)
Inland Power Limited
On the order dated 22.09.2020 passed in Case (T) No. 12 of 2019 for the Trueup of FY 2018-19 25.10.2024
1957 28 of 2024
N.T.P.C Ltd. Vrs. JBVNL
Seeking approval for taking E.H.T connection on 220 KV line from the respondent for contract demand of 2000 KVA. 27.09.2024
1956 Case No. 18 of 2024
Damodar Valley Corporation (DVC)  Versus
Green Valley ReneGreen Valley Renewable Energy Limited (GVREL)
Damodar Valley Corporation (DVC) and Green Valley Renewable Energy Limited (GVREL) has submitted an affidavited petition purported to be filed under clause 6.29 of JSERC (Terms and Conditions for Determination of Distribution Tariff) Regulations, 2020 for approval of power purchase agreement (PPA) between Damodar Valley Corporation and Green Valley Renewable Energy limited for purchase of 310 MW solar power by DVC. 27.09.2024
1955 Suo-Moto Case No. 02 of 2024
The Commission on its motion Versus 1.Jharkhand Bijli Vitran Nigam Limited 2.Jharkhand Urja Sancharan Nigam Limited & 3.The Secretary, Forest Deptt. Govt. of Jharkhand, Doranda
Death of Elephants in Chakulia area due to Electrocution 27.09.2024
1954 28 of 2024
N.T.P.C Ltd. Vrs. JBVNL
Seeking approval for taking E.H.T connection on 220 KV line from the respondent for contract demand of 2000 KVA. 24.09.2024
1953 27 of 2024
M/s Ramkrishna Forgings Limited Vrs. Jharkhanb Bijli Vitran Nigam Limited
Non-compliance of direction passed by Ld. VUSNF Chaibasa at Jamshedpur 24.09.2024
1952 26 of 2024
Tata Steel Limited
Review of order dt. 26/06/2024 in Case No. 08 of 2023 for True-up for FY 2022-23 , APR for FY 2023-24 and ARR & Tariff for FY 2024-25 24.09.2024
1951 25 of 2024
Tata Steel Utilities and Infrastructure Services Limited
Review of order dated 26.06.2024 passed by this Commission in Case (Tariff) No.09 of 2023 for true up for FY 2022-23, Annual Performance Review of FY 2023-24 and Aggregate Revenue Requirements & Tariff for FY 2024-25 24.09.2024
1950 24 of 2024
M/s ESL Steel Ltd. Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Exemption in compliance of Renewable Purchase Obligation for the period FY 2019-20 on the ground that the electricity produced from captive co- generating units of the petitioner is far in excess of its RPO requirements 24.09.2024
1949 23 of 2024
M/s ESL Steel Ltd. Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Exemption in compliance of Renewable Purchase Obligation for the period FY 2018-19 on the ground that the electricity produced from captive co- generating units of the petitioner is far in excess of its RPO requirements 24.09.2024
1948 22 of 2024
M/s ESL Steel Ltd. Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Exemption in compliance of Renewable Purchase Obligation for the period FY 2020-21 on the ground that the electricity produced from captive co- generating units of the petitioner is far in excess of its RPO requirements 24.09.2024
1947 21 of 2024
M/s Tata Power Company Limited Vrs. Tata Steel Limited (TSL)
Review of order dated 06.06.2024 passed by JSERC in Case (T) No. 11of 2023 for true-up for the FY 2022-23 and APR for FY 2023-24 with respect to unit 2 & 3 (2x120 MW) of Jojobera Power Plant of Tata Power Company Limited (TPCL) 24.09.2024
1946 Case No. 19 of 2024
 M/s Royal Instrument India Private Limited Versus Jharkhand Bijli Vitran Nigam Limited & Anr.
Seeking necessary approval to take H.T. Connection on 33 KV line from JBVNL having contract demand of 450 KVA. 24.09.2024
1945 10 of 2024
Amalgam Steel & Power Limited (ASPL) Vrs. JREDA
For seeking direction that the Captive Power Plant of the petitioner be treated as co-generation power plant and also for relaxation/exemption in compliance of RPO on total installed capacity of 30 MW, since 15 MW out of 30 MW Capacity Generation of Power by Petitioner Company is generated thorugh its waste heat recovery boiler (WHRB) 24.09.2024
1944 09 of 2024
Amalgam Steel & Power Limited (ASPL) Vrs. JREDA
For seekingdirection that the Captive Power Plant of the petitioner be treated as co-generation power plant and also for relaxation/exemption in compliance of RPO on total installed capacity of 30 MW, since 15 MW out of 30 MW Capacity Generation of Power by Petitioner Company is generated thorugh its waste heat recovery boiler (WHRB) from/for the year 2019-20 and 2020-21. 24.09.2024
1943 04 of 2024
 Tata Power Company Limited (TPCL) Vrs. Tata Steel Limited (TSL)
Review of order dated 09.01.2024 regarding True-up for FY 2021-22, Annual Performance Review for FY 2021-22, Annual Performance Review for FY 2022-23 with respect to Unit-2 & 3 (2x120 MW) of Jojobera Power Plant of the Tata Power Company Limited (TPCL) 24.09.2024
1942 17 of 2022
Inland Power Limited (IPL) Vrs. JUVNL & Ors
Review of order dated 04th November 2022 for True up for FY 2019-20 20.09.2024
1941 14 of 2024
Inland Power Limited (IPL)
Review of order dated 26.02.2024 regarding True-up for FY 2021-22 20.09.2024
1940 12 of 2019
Inland Power Limited
On the order dated 22.09.2020 passed in Case (T) No. 12 of 2019 for the Trueup of FY 2018-19 20.09.2024
1939 03 of 2024
Tata Steel Limited (TSL)
Review of the order dated 31.10.2023 passed in Case No. 30 of 2020 20.09.2024
1938 30 of 2024
Inland Power Limited (IPL)
Review of order dated 22.07.2024 w.r.t True-up for FY 2022-23 20.09.2024
1937 29 of 2024
 M/s Eastern Coalfields Limited Vrs. Jharkhand Urja Sancharan Nigam Limited & Ors
For direction upon the Respondent JUSNL to release the claim amount of Rs.32.97 Cr. which is the 80% of the operations & Maintenance (O&M) cost borned by the petitioner upto April 2015 20.09.2024
1936 18 of 2024
Damodar Valley Corporation (DVC)  Versus
Green Valley ReneGreen Valley Renewable Energy Limited (GVREL) 
Damodar Valley Corporation (DVC) and Green Valley Renewable Energy Limited (GVREL) has submitted an affidavited petition purported to be filed under clause 6.29 of JSERC (Terms and Conditions for Determination of Distribution Tariff) Regulations, 2020 for approval of power purchase agreement (PPA) between Damodar Valley Corporation and Green Valley Renewable Energy limited for purchase of 310 MW solar power by DVC. 02.08.2024
1935 14 of 2024
 Inland Power Limited (IPL)
Versus
Jharkhand Urja Vikas Nigam Limited & Ors.
Review of order dated 26.02.2024 regarding True-up for FY 2021-22 02.08.2024
1934 08 of 2024
 M/s Grasim Industry Limited Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Non-compliance of the order/direction dated 16.05.2023 passed by this Commission in Case No. 26 of 2020 02.08.2024
1933 Suo-Moto Case No. 02 of 2024
The Commission on its motion Versus 1.Jharkhand Bijli Vitran Nigam Limited 2.Jharkhand Urja Sancharan Nigam Limited & 3.The Secretary, Forest Deptt. Govt. of Jharkhand, Doranda
Death of Elephants in Chakulia area due to Electrocution 02.08.2024
1932 28 of 2023
Tata Steel Long Products Ltd. Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Petition purported to be filed under Section 86 (1)(f) of the Electricity Act 2003 read with clause A-13.12 of JSERC (Electricity Supply Code) Regulations 2015 & Clause A-45 of the JSERC (Conduct of Business) Regulations, 2016 interalia for direction upon the respondents to take a time bound decision upon the request made by the Petitioner seeking HT Industrial connection from the earlier CPP arrangement as contained in the letter dated 06.12.2022 effective from 01.07.2023 onwards for its steel plant at Gamharia 02.08.2024
1931 Case No. 03 of 2024
Tata Steel Limited
Versus
 Damodar Val Damodar Valley Corporation & Ors.
Review of the order dated 31.10.2023 passed in Case No. 30 of 2020 02.08.2024
1930 Case No. 17 of 2022
Inland Power Limited (IPL) Vrs. Jharkhand Urja Vikas Nigam Limited & Ors.
Review of order dated 04th November 2022 for True up for FY 2019-20 02.08.2024
1929 Case No. 19 of 2024
 M/s Royal Instrument India Private Limited Versus Jharkhand Bijli Vitran Nigam Limited & Anr.
Seeking necessary approval to take H.T. Connection on 33 KV line from JBVNL having contract demand of 450 KVA. 02.08.2024
1928 10 of 2024
Amalgam Steel & Power Limited (ASPL) Vrs. JREDA
For seeking direction that the Captive Power Plant of the petitioner be treated as co-generation power plant and also for relaxation/exemption in compliance of RPO on total installed capacity of 30 MW, since 15 MW out of 30 MW Capacity Generation of Power by Petitioner Company is generated thorugh its waste heat recovery boiler (WHRB) 01.08.2024
1927 09 of 2024
Amalgam Steel & Power Limited (ASPL) Vrs. JREDA
For seekingdirection that the Captive Power Plant of the petitioner be treated as co-generation power plant and also for relaxation/exemption in compliance of RPO on total installed capacity of 30 MW, since 15 MW out of 30 MW Capacity Generation of Power by Petitioner Company is generated thorugh its waste heat recovery boiler (WHRB) from/for the year 2019-20 and 2020-21. 01.08.2024
1926 04 of 2024
 Tata Power Company Limited (TPCL) Vrs. Tata Steel Limited (TSL)
Review of order dated 09.01.2024 regarding True-up for FY 2021-22, Annual Performance Review for FY 2021-22, Annual Performance Review for FY 2022-23 with respect to Unit-2 & 3 (2x120 MW) of Jojobera Power Plant of the Tata Power Company Limited (TPCL) 01.08.2024
1925 28 of 2023
 Tata Steel Long Products Ltd. Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Sub - Petition purported to be filed under Section 86 (1)(f) of the Electricity Act 2003 read with clause A-13.12 of JSERC (Electricity Supply Code) Regulations 2015 & Clause A-45 of the JSERC (Conduct of Business) Regulations, 2016 interalia for direction upon the respondents to take a time bound decision upon the request made by the Petitioner seeking HT Industrial connection from the earlier CPP arrangement as contained in the letter dated 06.12.2022 effective from 01.07.2023 onwards for its steel plant at Gamharia. 01.08.2024
1924 21 of 2024
M/s Tata Power Company Limited Vrs. Tata Steel Limited (TSL)
Review of order dated 06.06.2024 passed by JSERC in Case (T) No. 11of 2023 for true-up for the FY 2022-23 and APR for FY 2023-24 with respect to unit 2 & 3 (2x120 MW) of Jojobera Power Plant of Tata Power Company Limited (TPCL) 01.08.2024
1923 Case No. 17 of 2023
Adhunik Power and Natural resources Ltd. (APNRL) Versus Jharkhand Urja Vikas Nigam Limited & Ors.
Petition filed under Section 91 (1) (f) of the Electricity Act 2003 and Regulation 41 of the JSERC (Conduct of Business), Regulations 2016 seeking review of the Order dated 22.05.2023 passed by JSERC in Case (T) No. 02 of 2018 in the matter of True-up for FY 2016-17 and APR for FY 2017-18 in terms of provisions of the JSERC (Terms and Conditions for Determination of Generation Tariff), Regulations 2015 for supplying the regulated contracted capacity to JUVNL/JBVNL from 540 MW Coal based power plant of APNRL at Padapur and Srirampur villages in Seraikela Kharsawan District in the State of Jharkhand. 15.07.2024
1922 Case No. 23 of 2020 & MP No. 01 of 2022
Jharkhand Bijli Vitran Nigam Limited Versus Jharkhand Small Industries Association (JSIA)
Review of JSERC Tariff order for true up for FY 2018-19, Aggregate Revenue Requirement and Tariff for FY 2020-21 for JBVNL. 08.07.2024
1921 Case No. 37 of 2023
Pasari Steel Pvt. Limited Versus Jharkhand Bijli Vitran Nigam Limited (JBVNL) & Ors
Direction upon the Respondents to comply with the order dated 22.04.2008 passed by the learned CGRF, Ranchi in Case No.04/08 affirmed by the order dated 30.08.2008 passed by the Electricity Ombudsman in Case No. EOJ/17/2008 and to refund the amount with interest forthwith in so far ase in some cases amounts have already been released by adjusting the amount against KVA charges. 08.07.2024
1920 Case (Tariff) No. 09 of 2020
Damodary Valley Corporation (DVC)
Versus
 Association of DVC HT Consumers of Jharkhand & Ors.
Determination of Consumer Category-wise tariff for the period 2006-07 to FY 2011-12 for distribution and retail supply of Electricity for the post of the Damodar Valley Area failing within the teritory of the state of Jharkhand. 28.06.2024
1919 05 of 2024
M/s Gajanan Ferro Pvt. Ltd. Vrs. Jharkhand Urja Vikas Nigam Limited (JUVNL)
For getting/retaining the existing 33 KV supply of power with enhanced contract demand of 24000 KVA 28.06.2024
1918 Case No. 18 of 2024
Damodar Valley Corporation (DVC)  Versus
Green Valley ReneGreen Valley Renewable Energy Limited (GVREL) 
Damodar Valley Corporation (DVC) and Green Valley Renewable Energy Limited (GVREL) has submitted an affidavited petition purported to be filed under clause 6.29 of JSERC (Terms and Conditions for Determination of Distribution Tariff) Regulations, 2020 for approval of power purchase agreement (PPA) between Damodar Valley Corporation and Green Valley Renewable Energy limited for purchase of 310 MW solar power by DVC. 28.06.2024
1917 Suo-Moto Case No. 02 of 2024
The Commission on its motion Versus 1.Jharkhand Bijli Vitran Nigam Limited 2.Jharkhand Urja Sancharan Nigam Limited & 3.The Secretary, Forest Deptt. Govt. of Jharkhand, Doranda
Death of Elephants in Chakulia area due to Electrocution 21.06.2024
1916 14 of 2024
Inland Power Limited (IPL)
Review of order dated 26.02.2024 regarding True-up for FY 2021-22 21.06.2024
1915 08 of 2024
 M/s Grasim Industry Limited Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Non-compliance of the order/direction dated 16.05.2023 passed by this Commission in Case No. 26 of 2020 21.06.2024
1914 Case No. 03 of 2024
Tata Steel Limited
Versus
 Damodar Val Damodar Valley Corporation & Ors.s
Review of the order dated 31.10.2023 passed in Case No. 30 of 2020 21.06.2024
1913 28 of 2023
Tata Steel Long Products Ltd. Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Petition purported to be filed under Section 86 (1)(f) of the Electricity Act 2003 read with clause A-13.12 of JSERC (Electricity Supply Code) Regulations 2015 & Clause A-45 of the JSERC (Conduct of Business) Regulations, 2016 interalia for direction upon the respondents to take a time bound decision upon the request made by the Petitioner seeking HT Industrial connection from the earlier CPP arrangement as contained in the letter dated 06.12.2022 effective from 01.07.2023 onwards for its steel plant at Gamharia 21.06.2024
1912 Case No. 17 of 2022
Inland Power Limited (IPL) Versus Jharkhand Urja Vikas Nigam Limited (JUVNL)& Ors
Review of order dated 04th November 2022 for True up for FY 2019-20 21.06.2024
1911 05 of 2024
M/s Gajanan Ferro Pvt. Ltd. Vrs. Jharkhand Urja Vikas Nigam Limited (JUVNL)
For getting/retaining the existing 33 KV supply of power with enhanced contract demand of 24000 KVA 04.06.2024
1910 Case No. 15 of 2024
M/s Dayton Grains Pvt. Ltd. Vrs. JUVNL & Ors
For seeking necessary approval to take new service H.T connection from JBVNL at supply voltage of 33 kv having 700 KVA contract demand 04.06.2024
1909 06 of 2024
M/s Khetan Enterprises Vrs. Jharkhand Bijli Vitran Nigam Limited & Another
For seeking necessary approval to take allow it to take HT Connection at contract demand of 500 KVA to 600 KVA on 33 KV line from JBVNL. 04.06.2024
1908 Case  No.  10 of 2024
Amalgam Steel & Power Limited (ASPL)
Versus
 Jharkhand Renewable Energy Development
For seeking direction that the Captive Power Plant of the petitioner be treated as co-generation power plant and also for relaxation/exemption in compliance of RPO on total installed capacity of 30 MW, since 15 MW out of 30 MW Capacity Generation of Power by Petitioner Company is generated thorugh its waste heat recovery boiler (WHRB) 04.06.2024
1907 Case  No.  09 of 2024
Amalgam Steel & Power Limited (ASPL)
Versus
 Jharkhand Renewable Energy Development
For seeking direction that the Captive Power Plant of the petitioner be treated as co-generation power plant and also for relaxation/exemption in compliance of RPO on total installed capacity of 30 MW, since 15 MW out of 30 MW Capacity Generation of Power by Petitioner Company is generated thorugh its waste heat recovery boiler (WHRB) from/for the year 2019-20 and 2020-21. 04.06.2024
1906 Case (Tariff) No. 09 of 2020
Damodary Valley Corporation (DVC)
Versus
 Association of DVC HT Consumers of Jharkhand & Ors.
Determination of Consumer Category-wise tariff for the period 2006-07 to FY 2011-12 for distribution and retail supply of Electricity for the post of the Damodar Valley Area failing within the teritory of the state of Jharkhand. 24.05.2024
1905 Case No. 14 of 2024
 Inland Power Limited (IPL)
Versus
Jharkhand Urja Vikas Nigam Limited & Ors.
Review of order dated 26.02.2024 regarding True-up for FY 2021-22 24.05.2024
1904 28 of 2023
Tata Steel Long Products Ltd. Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Petition purported to be filed under Section 86 (1)(f) of the Electricity Act 2003 read with clause A-13.12 of JSERC (Electricity Supply Code) Regulations 2015 & Clause A-45 of the JSERC (Conduct of Business) Regulations, 2016 interalia for direction upon the respondents to take a time bound decision upon the request made by the Petitioner seeking HT Industrial connection from the earlier CPP arrangement as contained in the letter dated 06.12.2022 effective from 01.07.2023 onwards for its steel plant at Gamharia 24.05.2024
1903 15 of 2024
M/s Dayton Grains Pvt. Ltd. Vrs. JUVNL & Ors
For seeking necessary approval to take new service H.T connection from JBVNL at supply voltage of 33 kv having 700 KVA contract demand 24.05.2024
1902 17 of 2024
Tata Steel Utilities and Infrastructure Services Limited (TSUISL)
For approval of proposed changes required to be implemented in existing Distribution Tariff Regulations 17.05.2024
1901 Suo-Moto Case No. 02 of 2024
The Commission on its motion Versus 1.Jharkhand Bijli Vitran Nigam Limited 2.Jharkhand Urja Sancharan Nigam Limited & 3.The Secretary, Forest Deptt. Govt. of Jharkhand, Doranda
Death of Elephants in Chakulia area due to Electrocution 17.05.2024
1900 16 of 2024
 Rajyash Agro Pvt. Ltd. Vrs. Jharkhand Bijli Vitran Nigam Limited
For approval to take new service H.T.Connection from JBVNL at supply voltage of 33 KV having 800 KVA contract demand 17.05.2024
1899 06 of 2024
M/s Khetan Enterprises Vrs. Jharkhand Bijli Vitran Nigam Limited & Another
For seeking necessary approval to take allow it to take HT Connection at contract demand of 500 KVA to 600 KVA on 33 KV line from JBVNL. 17.05.2024
1898 05 of 2024
M/s Gajanan Ferro Pvt. Ltd. Vrs. Jharkhand Urja Vikas Nigam Limited (JUVNL)
For getting/retaining the existing 33 KV supply of power with enhanced contract demand of 24000 KVA 17.05.2024
1897 28 of 2023
Tata Steel Long Products Ltd. Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Petition purported to be filed under Section 86 (1)(f) of the Electricity Act 2003 read with clause A-13.12 of JSERC (Electricity Supply Code) Regulations 2015 & Clause A-45 of the JSERC (Conduct of Business) Regulations, 2016 interalia for direction upon the respondents to take a time bound decision upon the request made by the Petitioner seeking HT Industrial connection from the earlier CPP arrangement as contained in the letter dated 06.12.2022 effective from 01.07.2023 onwards for its steel plant at Gamharia 17.05.2024
1896 08 of 2024
 M/s Grasim Industry Limited Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Non-compliance of the order/direction dated 16.05.2023 passed by this Commission in Case No. 26 of 2020 17.05.2024
1895 Case No. 15 of 2024
M/s Dayton Grains Pvt. Ltd. Vrs. JUVNL & Ors
For seeking necessary approval to take new service H.T connection from JBVNL at supply voltage of 33 kv having 700 KVA contract demand 17.05.2024
1894 Case No. 17 of 2022
Inland Power Limited (IPL) Vrs. Jharkhand Urja Vikas Nigam Limited & Ors.
Review of order dated 04th November 2022 for True up for FY 2019-20 17.05.2024
1893 01 of 2022
SAIL, Bokaro Steel Plant Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Petition purported to be filed under Regulations 13 read with 15.2 of the JSERC (Renewable Purchase Obligation and its compliance) Regulations, 2016 for exemption from RPO compliance for the period 2016-17, 2017-18, 2018-19, 2019-20, 2020-21 and further periods in terms of 2016 and 2021 (First amendment) Regulations. 17.05.2024
1892 36 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2020-21 17.05.2024
1891 35 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2019-20 17.05.2024
1890 34 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemptioin from RPO for FY 2018-19 17.05.2024
1889 33 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2017-18 17.05.2024
1888 32 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2016-17 17.05.2024
1887 31 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2015-16 17.05.2024
1886 30 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2014-15 17.05.2024
1885 29 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2013-14 17.05.2024
1884 37 of 2023
Pasari Steel Pvt. Ltd. Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Direction upon the Respondents to comply with the order dated 22.04.2008 passed by the learned CGRF, Ranchi in Case No.04/08 affirmed by the order dated 30.08.2008 passed by the Electricity Ombudsman in Case No. EOJ/17/2008 and to refund the amount with interest forthwith in so far ase in some cases amounts have already been released by adjusting the amount against KVA charges. 14.05.2024
1883 Case No. 17 of 2023
Adhunik Power and Natural resources Ltd. (APNRL) Versus Jharkhand Urja Vikas Nigam Limited & Ors.
Petition filed under Section 91 (1) (f) of the Electricity Act 2003 and Regulation 41 of the JSERC (Conduct of Business), Regulations 2016 seeking review of the Order dated 22.05.2023 passed by JSERC in Case (T) No. 02 of 2018 in the matter of True-up for FY 2016-17 and APR for FY 2017-18 in terms of provisions of the JSERC (Terms and Conditions for Determination of Generation Tariff), Regulations 2015 for supplying the regulated contracted capacity to JUVNL/JBVNL from 540 MW Coal based power plant of APNRL at Padapur and Srirampur villages in Seraikela Kharsawan District in the State of Jharkhand. 14.05.2024
1882 Case No. 14 of 2024
 Inland Power Limited (IPL)
Versus
Jharkhand Urja Vikas Nigam Limited & Ors.
Review of order dated 26.02.2024 regarding True-up for FY 2021-22 10.05.2024
1881 Case No. 04 of 2024
Tata Power Company Limited. Versus
Tata Steel Limited
Review of order dated 09.01.2024 regarding True-up for FY 2021-22, Annual Performance Review for FY 2021-22, Annual Performance Review for FY 2022-23 with respect to Unit-2 & 3 (2x120 MW) of Jojobera Power Plant of the Tata Power Company Limited (TPCL) 10.05.2024
1880 Case No. 03 of 2024
Tata Steel Limited
Versus
 Damodar Val Damodar Valley Corporation & Ors.
Review of the order dated 31.10.2023 passed in Case No. 30 of 2020 10.05.2024
1879 Case No. 27 of 2023
 AMP Energy C & I Fifteen Private Limited Versus Jharkhand Urja Vikas Nigam Limited & Ors.
Petition under section 86 (1)(c) & (e) & (k) of the Electricity Act, 2003 read with regulation 55.3 of the Jharkhand State Electricity Regulatory Commission (Conduct of Business) Regulations, 2016 seeking appropriate reliefs/directions vis a vis the Jharkhand State Solar Policy, 2022 for supply of solar power from its under developing captive solar project. 10.05.2024
1878 Case (Tariff) No. 09 of 2020
Damodary Valley Corporation (DVC)
Versus
 Association of DVC HT Consumers of Jharkhand & Ors.
Determination of Consumer Category-wise tariff for the period 2006-07 to FY 2011-12 for distribution and retail supply of Electricity for the post of the Damodar Valley Area failing within the teritory of the state of Jharkhand. 10.05.2024
1877 Case  No.  10 of 2024
Amalgam Steel & Power Limited (ASPL)
Versus
 Jharkhand Renewable Energy Development
For seeking direction that the Captive Power Plant of the petitioner be treated as co-generation power plant and also for relaxation/exemption in compliance of RPO on total installed capacity of 30 MW, since 15 MW out of 30 MW Capacity Generation of Power by Petitioner Company is generated thorugh its waste heat recovery boiler (WHRB) 10.05.2024
1876 Case  No.  09 of 2024
Amalgam Steel & Power Limited (ASPL)
Versus
 Jharkhand Renewable Energy Development
For seeking direction that the Captive Power Plant of the petitioner be treated as co-generation power plant and also for relaxation/exemption in compliance of RPO on total installed capacity of 30 MW, since 15 MW out of 30 MW Capacity Generation of Power by Petitioner Company is generated thorugh its waste heat recovery boiler (WHRB) from/for the year 2019-20 and 2020-21. 10.05.2024
1875 Suo-Moto Case No. 02 of 2024
The Commission on its motion Versus 1.Jharkhand Bijli Vitran Nigam Limited 2.Jharkhand Urja Sancharan Nigam Limited & 3.The Secretary, Forest Deptt. Govt. of Jharkhand, Doranda
Death of Elephants in Chakulia area due to Electrocution 09.05.2024
1874 Case No. 15 of 2024
M/s Dayton Grains Pvt. Ltd. Vrs. JUVNL & Ors
For seeking necessary approval to take new service H.T connection from JBVNL at supply voltage of 33 kv having 700 KVA contract demand 30.04.2024
1873 08 of 2024
 M/s Grasim Industry Limited Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Non-compliance of the order/direction dated 16.05.2023 passed by this Commission in Case No. 26 of 2020 30.04.2024
1872 06 of 2024
M/s Khetan Enterprises Vrs. Jharkhand Bijli Vitran Nigam Limited & Another
For seeking necessary approval to take allow it to take HT Connection at contract demand of 500 KVA to 600 KVA on 33 KV line from JBVNL. 30.04.2024
1871 28 of 2023
Tata Steel Long Products Ltd. Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Petition purported to be filed under Section 86 (1)(f) of the Electricity Act 2003 read with clause A-13.12 of JSERC (Electricity Supply Code) Regulations 2015 & Clause A-45 of the JSERC (Conduct of Business) Regulations, 2016 interalia for direction upon the respondents to take a time bound decision upon the request made by the Petitioner seeking HT Industrial connection from the earlier CPP arrangement as contained in the letter dated 06.12.2022 effective from 01.07.2023 onwards for its steel plant at Gamharia 30.04.2024
1870 05 of 2024
M/s Gajanan Ferro Pvt. Ltd. Vrs. Jharkhand Urja Vikas Nigam Limited (JUVNL)
For getting/retaining the existing 33 KV supply of power with enhanced contract demand of 24000 KVA 30.04.2024
1869 16 of 2024
 Rajyash Agro Pvt. Ltd. Vrs. Jharkhand Bijli Vitran Nigam Limited
For approval to take new service H.T.Connection from JBVNL at supply voltage of 33 KV having 800 KVA contract demand 30.04.2024
1868 12 of 2024
Inland Power Limited Vrs. Jharkhand Bijli Vitran Nigam Limited
For approval of 5th Supplementary Power Purchase Agreement (PPA) under Shakti Scheme B-II Round VI for 110100 tons of Coal 19.04.2024
1867 11 of 2024
Adhunik Power and Natural Resources Limited Vrs. Jharkhand Bijli Vitran Nigam Limited
For approval of the Draft Addendum no.04 to the PPA dated 28.09.2012 to be executed between JBVNL and APNRL in terms of the sixth round of auction of coal linkages under paragraph b(ii) of the shakti policy 2017 19.04.2024
1866 36 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2020-21 19.04.2024
1865 35 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2019-20 19.04.2024
1864 34 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemptioin from RPO for FY 2018-19 19.04.2024
1863 33 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2017-18 19.04.2024
1862 32 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2016-17 19.04.2024
1861 31 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2015-16 19.04.2024
1860 30 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2014-15 19.04.2024
1859 29 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2013-14 19.04.2024
1858 Case No. 17 of 2022
Inland Power Limited (IPL) Vrs. Jharkhand Urja Vikas Nigam Limited & Ors.
Review of order dated 04th November 2022 for True up for FY 2019-20 19.04.2024
1857 01 of 2022
SAIL, Bokaro Steel Plant Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Petition purported to be filed under Regulations 13 read with 15.2 of the JSERC (Renewable Purchase Obligation and its compliance) Regulations, 2016 for exemption from RPO compliance for the period 2016-17, 2017-18, 2018-19, 2019-20, 2020-21 and further periods in terms of 2016 and 2021 (First amendment) Regulations. 19.04.2024
1856 Case (Tariff) No. 09 of 2020 Damodar Valley Corporation (DVC) Determination of Consumer Category-wise tariff for the period 2006-07 to FY 2011-12 for distribution and retail supply of Electricity for the post of the Damodar Valley Area failing within the teritory of the state of Jharkhand. 16.04.2024
1855 37 of 2023
Pasari Steel Pvt. Ltd. Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Direction upon the Respondents to comply with the order dated 22.04.2008 passed by the learned CGRF, Ranchi in Case No.04/08 affirmed by the order dated 30.08.2008 passed by the Electricity Ombudsman in Case No. EOJ/17/2008 and to refund the amount with interest forthwith in so far ase in some cases amounts have already been released by adjusting the amount against KVA charges. 16.04.2024
1854 17 of 2023
Adhunik Power and Natural Resources Limited Vrs. Jharkhand Urja Vikas Nigam Limited & Ors.
Petition filed under Section 91 (1) (f) of the Electricity Act 2003 and Regulation 41 of the JSERC (Conduct of Business), Regulations 2016 seeking review of the Order dated 22.05.2023 passed by JSERC in Case (T) No. 02 of 2018 in the matter of True-up for FY 2016-17 and APR for FY 2017-18 in terms of provisions of the JSERC (Terms and Conditions for Determination of Generation Tariff), Regulations 2015 for supplying the regulated contracted capacity to JUVNL/JBVNL from 540 MW Coal based power plant of APNRL at Padapur and Srirampur villages in Seraikela Kharsawan District in the State of Jharkhand. 16.04.2024
1853 14 of 2024
Inland Power Limited (IPL)
Review of order dated 26.02.2024 regarding True-up for FY 2021-22 16.04.2024
1852 13 of 2024
Jharkhand Urja Utpadan Nigam Limited
Review of order dated 26.02.2024 regarding True-up for FY 2016-17 to FY 2020-21 & Business Plan, Tariff,MYT tariff petition for control period FY 21-22 to FY 25-26. 16.04.2024
1851 Suo-Moto Case No. 02 of 2024
The Commission on its motion Versus 1.Jharkhand Bijli Vitran Nigam Limited 2.Jharkhand Urja Sancharan Nigam Limited & 3.The Secretary, Forest Deptt. Govt. of Jharkhand, Doranda
Death of Elephants in Chakulia area due to Electrocution 16.04.2024
1850 Case No. 15 of 2024
M/s Dayton Grains Pvt. Ltd. Vrs. JUVNL & Ors
For seeking necessary approval to take new service H.T connection from JBVNL at supply voltage of 33 kv having 700 KVA contract demand 02.04.2024
1849 Case (Tariff) No. 09 of 2020 Damodar Valley Corporation (DVC) Determination of Consumer Category-wise tariff for the period 2006-07 to FY 2011-12 for distribution and retail supply of Electricity for the post of the Damodar Valley Area failing within the teritory of the state of Jharkhand. 02.04.2024
1848 12 of 2024
Inland Power Limited Vrs. Jharkhand Bijli Vitran Nigam Limited
For approval of 5th Supplementary Power Purchase Agreement (PPA) under Shakti Scheme B-II Round VI for 110100 tons of Coal 02.04.2024
1847 11 of 2024
Adhunik Power and Natural Resources Limited Vrs. Jharkhand Bijli Vitran Nigam Limited
For approval of the Draft Addendum no.04 to the PPA dated 28.09.2012 to be executed between JBVNL and APNRL in terms of the sixth round of auction of coal linkages under paragraph b(ii) of the shakti policy 2017 02.04.2024
1846 08 of 2024
 M/s Grasim Industry Limited Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Non-compliance of the order/direction dated 16.05.2023 passed by this Commission in Case No. 26 of 2020 02.04.2024
1845 07 of 2024
Tata Steel Utilities and Infrastructure Services Limited (TSUISL)
Approval of capital expenditure for " Installation of 1x80/100 MVA 132/33 KV transformer and related interconnecting switchgears for TGS substation" related to network augmentation, safety & reliability by the Licensee Tata Steel UISL 02.04.2024
1844 06 of 2024
M/s Khetan Enterprises Vrs. Jharkhand Bijli Vitran Nigam Limited & Another
For seeking necessary approval to take allow it to take HT Connection at contract demand of 500 KVA to 600 KVA on 33 KV line from JBVNL. 02.04.2024
1843 05 of 2024
 M/s Gajanan Ferro Pvt. Ltd. Vrs. Jharkhand Urja Vikas Nigam Limited (JUVNL)
For getting/retaining the existing 33 KV supply of power with enhanced contract demand of 24000 KVA 02.04.2024
1842 38 of 2023
Steel Authority of India Ltd. Vrs. Damodar Valley Corporation
Petition filed under Section 94 (1) (f) of the Electricity Act, 2003 read with Regulation 41.1 of the JSERC (Conduct of Business) Regulations, 2016 for review of order dt. 12/06/2023 passed in Case No. 29 of 2020 along with application under section 5 of the limitation Act, 1963 for condonation of delay of 43 days is filing the review petition. 02.04.2024
1841 23 of 2020 & Miscellaneous Petition No 01 of 2022
Jharkhand Small Industries Association (JSIA) Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Review of JSERC Tariff order for true up for FY 2018-19, Aggregate Revenue Requirement and Tariff for FY 2020-21 for JBVNL. 02.04.2024
1840 28 of 2023
 Tata Steel Long Products Ltd. Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Direction upon the respondents to take a time bound decision upon the request made by the Petitioner seeking HT Industrial connection from the earlier CPP arrangement as contained in the letter dated 06.12.2022 effective from 01.07.2023 onwards for its steel plant at Gamharia. 02.04.2024
1839 Case No. 27 of 2023
 AMP Energy C & I Fifteen Private Limited Versus Jharkhand Urja Vikas Nigam Limited & Ors.
Petition under section 86 (1)(c) & (e) & (k) of the Electricity Act, 2003 read with regulation 55.3 of the Jharkhand State Electricity Regulatory Commission (Conduct of Business) Regulations, 2016 seeking appropriate reliefs/directions vis a vis the Jharkhand State Solar Policy, 2022 for supply of solar power from its under developing captive solar project. 02.04.2024
1838 Suo-Moto Case No. 02 of 2024
The Commission on its motion Versus 1.Jharkhand Bijli Vitran Nigam Limited 2.Jharkhand Urja Sancharan Nigam Limited & 3.The Secretary, Forest Deptt. Govt. of Jharkhand, Doranda
Death of Elephants in Chakulia area due to Electrocution 15.03.2024
1837 37 of 2023
Pasari Steel Pvt. Ltd. Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Direction upon the Respondents to comply with the order dated 22.04.2008 passed by the learned CGRF, Ranchi in Case No.04/08 affirmed by the order dated 30.08.2008 passed by the Electricity Ombudsman in Case No. EOJ/17/2008 and to refund the amount with interest forthwith in so far ase in some cases amounts have already been released by adjusting the amount against KVA charges. 15.03.2024
1836 Case No. 17 of 2023
Adhunik Power and Natural resources Ltd. (APNRL) Versus Jharkhand Urja Vikas Nigam Limited & Ors.
Petition filed under Section 91 (1) (f) of the Electricity Act 2003 and Regulation 41 of the JSERC (Conduct of Business), Regulations 2016 seeking review of the Order dated 22.05.2023 passed by JSERC in Case (T) No. 02 of 2018 in the matter of True-up for FY 2016-17 and APR for FY 2017-18 in terms of provisions of the JSERC (Terms and Conditions for Determination of Generation Tariff), Regulations 2015 for supplying the regulated contracted capacity to JUVNL/JBVNL from 540 MW Coal based power plant of APNRL at Padapur and Srirampur villages in Seraikela Kharsawan District in the State of Jharkhand. 15.03.2024
1835 Case No. 17 of 2022
Inland Power Limited (IPL) Vrs. Jharkhand Urja Vikas Nigam Limited & Ors.
Review of order dated 04th November 2022 for True up for FY 2019-20 15.03.2024
1834 01 of 2022
SAIL, Bokaro Steel Plant Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Petition purported to be filed under Regulations 13 read with 15.2 of the JSERC (Renewable Purchase Obligation and its compliance) Regulations, 2016 for exemption from RPO compliance for the period 2016-17, 2017-18, 2018-19, 2019-20, 2020-21 and further periods in terms of 2016 and 2021 (First amendment) Regulations. 15.03.2024
1833 Case No. 04 of 2024
Tata Power Company Limited. Versus
Tata Steel Limited
Review of order dated 09.01.2024 regarding True-up for FY 2021-22, Annual Performance Review for FY 2021-22, Annual Performance Review for FY 2022-23 with respect to Unit-2 & 3 (2x120 MW) of Jojobera Power Plant of the Tata Power Company Limited (TPCL) 15.03.2024
1832 Case No. 03 of 2024
Tata Steel Limited
Versus
 Damodar Val Damodar Valley Corporation & Ors.
Review of the order dated 31.10.2023 passed in Case No. 30 of 2020 15.03.2024
1831 36 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2020-21 15.03.2024
1830 35 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2019-20 15.03.2024
1829 34 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemptioin from RPO for FY 2018-19 15.03.2024
1828 33 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2017-18 15.03.2024
1827 32 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2016-17 15.03.2024
1826 31 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2015-16 15.03.2024
1825 30 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2014-15 15.03.2024
1824 29 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2013-14 15.03.2024
1823 38 of 2023
Steel Authority of India Ltd. Vrs. Damodar Valley Corporation
Petition filed under Section 94 (1) (f) of the Electricity Act, 2003 read with Regulation 41.1 of the JSERC (Conduct of Business) Regulations, 2016 for review of order dt. 12/06/2023 passed in Case No. 29 of 2020 along with application under section 5 of the limitation Act, 1963 for condonation of delay of 43 days is filing the review petition. 20.02.2024
1822 23 of 2020 & Miscellaneous Petition No 01 of 2022
Jharkhand Small Industries Association (JSIA) Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Review of JSERC Tariff order for true up for FY 2018-19, Aggregate Revenue Requirement and Tariff for FY 2020-21 for JBVNL. 20.02.2024
1821 28 of 2023
 Tata Steel Long Products Ltd. Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Direction upon the respondents to take a time bound decision upon the request made by the Petitioner seeking HT Industrial connection from the earlier CPP arrangement as contained in the letter dated 06.12.2022 effective from 01.07.2023 onwards for its steel plant at Gamharia. 20.02.2024
1820 36 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2020-21 20.02.2024
1819 35 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2019-20 20.02.2024
1818 34 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemptioin from RPO for FY 2018-19 20.02.2024
1817 33 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2017-18 20.02.2024
1816 32 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2016-17 20.02.2024
1815 31 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2015-16 20.02.2024
1814 30 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2014-15 20.02.2024
1813 29 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2013-14 20.02.2024
1812 01 of 2022
SAIL, Bokaro Steel Plant Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Petition purported to be filed under Regulations 13 read with 15.2 of the JSERC (Renewable Purchase Obligation and its compliance) Regulations, 2016 for exemption from RPO compliance for the period 2016-17, 2017-18, 2018-19, 2019-20, 2020-21 and further periods in terms of 2016 and 2021 (First amendment) Regulations. 20.02.2024
1811 Case No. 09 of 2019
M/s Vananchal Steel Alloys Private Limited Versus Damodar Valley Corporation & another
Order on Case No. 09 of 2019 20.02.2024
1810 Case No. 27 of 2023
 AMP Energy C & I Fifteen Private Limited Versus Jharkhand Urja Vikas Nigam Limited & Ors.
Petition under section 86 (1)(c) & (e) & (k) of the Electricity Act, 2003 read with regulation 55.3 of the Jharkhand State Electricity Regulatory Commission (Conduct of Business) Regulations, 2016 seeking appropriate reliefs/directions vis a vis the Jharkhand State Solar Policy, 2022 for supply of solar power from its under developing captive solar project. 20.02.2024
1809 Adjudicate Case No. 01 of 2023/ Case No.15 of 2023
The Bureau of Energy Efficiency
Vrs.
Jharkhand Bijli Vitran Nigam Limited
Petition filed under section 27 of the Energy Conservation Act, 2001 for adjudication of the penalty under Section 26 of the Energy Conservatin Act, 2001 by the Adujdication office and for directions to Jharkhand Bijli Vitran Nigam Limited to make payment as adjuicated by the Adjudicating officer. 09.02.2024
1808 38 of 2023
Steel Authority of India Ltd. Vrs. Damodar Valley Corporation
Petition filed under Section 94 (1) (f) of the Electricity Act, 2003 read with Regulation 41.1 of the JSERC (Conduct of Business) Regulations, 2016 for review of order dt. 12/06/2023 passed in Case No. 29 of 2020 along with application under section 5 of the limitation Act, 1963 for condonation of delay of 43 days is filing the review petition. 06.02.2024
1807 37 of 2023
Pasari Steel Pvt. Ltd. Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Direction upon the Respondents to comply with the order dated 22.04.2008 passed by the learned CGRF, Ranchi in Case No.04/08 affirmed by the order dated 30.08.2008 passed by the Electricity Ombudsman in Case No. EOJ/17/2008 and to refund the amount with interest forthwith in so far ase in some cases amounts have already been released by adjusting the amount against KVA charges. 06.02.2024
1806 23 of 2023
 Inland Power Limited
For review of order dated 22.05.2023 regarding Truing up for FY 2020-21 of Inland Power Limited 06.02.2024
1805 Case No. 17 of 2023
Adhunik Power and Natural resources Ltd. (APNRL) Versus Jharkhand Urja Vikas Nigam Limited & Ors.
Petition filed under Section 91 (1) (f) of the Electricity Act 2003 and Regulation 41 of the JSERC (Conduct of Business), Regulations 2016 seeking review of the Order dated 22.05.2023 passed by JSERC in Case (T) No. 02 of 2018 in the matter of True-up for FY 2016-17 and APR for FY 2017-18 in terms of provisions of the JSERC (Terms and Conditions for Determination of Generation Tariff), Regulations 2015 for supplying the regulated contracted capacity to JUVNL/JBVNL from 540 MW Coal based power plant of APNRL at Padapur and Srirampur villages in Seraikela Kharsawan District in the State of Jharkhand. 06.02.2024
1804 Suo-Moto Case No. 02 of 2024
The Commission on its motion Versus 1.Jharkhand Bijli Vitran Nigam Limited 2.Jharkhand Urja Sancharan Nigam Limited & 3.The Secretary, Forest Deptt. Govt. of Jharkhand, Doranda
Death of Elephants in Chakulia area due to Electrocution 06.02.2024
1803 Case No. 03 of 2024
Tata Steel Limited
Versus
 Damodar Val Damodar Valley Corporation & Ors.
Review of the order dated 31.10.2023 passed in Case No. 30 of 2020 06.02.2024
1802 Miscellaneous Petition No. 05 of 2023
Jharkhand Bijli Vitran Nigam Limited
An affidavitated miscellaneous petition purported to be filed under Section 61, 86 and Section 181 of the Electricity Act 2003 for formulation of Regulatioin on installation and implementation of Prepaid Smart Metering in the State of Jharkhand 06.02.2024
1801 01 of 2024
M/s Inland Power Limited (IPL)
Vrs.
Jharkhand Bijli Vitran Nigam Limited (JBVNL)
For approval of draft 4th supplementary Power Purchase Agreement dated 23.02.2012 signed between JBVNL & M/s Inland Power Limited 24.01.2024
1800 Adjudicate Case No. 01 of 2023/ Case No.15 of 2023
The Bureau of Energy Efficiency
Vrs.
Jharkhand Bijli Vitran Nigam Limited
Petition filed under section 27 of the Energy Conservation Act, 2001 for adjudication of the penalty under Section 26 of the Energy Conservatin Act, 2001 by the Adujdication office and for directions to Jharkhand Bijli Vitran Nigam Limited to make payment as adjuicated by the Adjudicating officer. 24.01.2024
1799 Case No. 23 of 2020 & MP No. 01 of 2022
Jharkhand Bijli Vitran Nigam Limited Versus Jharkhand Small Industries Association (JSIA)
Review of JSERC Tariff order for true up for FY 2018-19, Aggregate Revenue Requirement and Tariff for FY 2020-21 for JBVNL. 19.01.2024
1798 36 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2020-21 16.01.2024
1797 35 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2019-20 16.01.2024
1796 34 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemptioin from RPO for FY 2018-19 16.01.2024
1795 33 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2017-18 16.01.2024
1794 32 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2016-17 16.01.2024
1793 31 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2015-16 16.01.2024
1792 30 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2014-15 16.01.2024
1791 29 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2013-14 16.01.2024
1790 Case No. 01 of 2022
SAIL, Bokaro Steel Plant
Versus
 Jharkhand Renewable Energy Development Agency (JREDA)
Petition purported to be filed under Regulations 13 read with 15.2 of the JSERC (Renewable Purchase Obligation and its compliance) Regulations, 2016 for exemption from RPO compliance for the period 2016-17, 2017-18, 2018-19, 2019-20, 2020-21 and further periods in terms of 2016 and 2021 (First amendment) Regulations. 16.01.2024
1789 28 of 2023
 Tata Steel Long Products Ltd. Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Direction upon the respondents to take a time bound decision upon the request made by the Petitioner seeking HT Industrial connection from the earlier CPP arrangement as contained in the letter dated 06.12.2022 effective from 01.07.2023 onwards for its steel plant at Gamharia. 16.01.2024
1788 Case No. 17 of 2022
Inland Power Limited (IPL) Vrs. Jharkhand Urja Vikas Nigam Limited & Ors.
Review of order dated 04th November 2022 for True up for FY 2019-20 16.01.2024
1787 Case No. 09 of 2019
M/s Vananchal Steel Alloys Private Limited Versus Damodar Valley Corporation & another
Order on Case No. 09 of 2019 16.01.2024
1786 Case No. 27 of 2023
 AMP Energy C & I Fifteen Private Limited Versus Jharkhand Urja Vikas Nigam Limited & Ors.
Petition under section 86 (1)(c) & (e) & (k) of the Electricity Act, 2003 read with regulation 55.3 of the Jharkhand State Electricity Regulatory Commission (Conduct of Business) Regulations, 2016 seeking appropriate reliefs/directions vis a vis the Jharkhand State Solar Policy, 2022 for supply of solar power from its under developing captive solar project. 12.01.2024
1785 23 of 2023
 Inland Power Limited
For review of order dated 22.05.2023 regarding Truing up for FY 2020-21 of Inland Power Limited 12.01.2024
1784 Case No.21 of 2023
 Jharkhand Urja Sancharan Nigam Limited
Review of order dated 23.06.2023 for True up for FY 2019-20 and Business Plan & Multi Year Tariff for the Control Period FY 2021-22 to FY 2025-26 12.01.2024
1783 19 of 2023
Jharkhand Urja Sancharan Nigam Limited (JUSNL)
Review of order dated 12.06.2023 for True up for FY 2017-18 12.01.2024
1782 Case No. 17 of 2023
Adhunik Power and Natural resources Ltd. (APNRL)
Versus
 Jharkhand Urja Vikas Nigam Limited & Ors.
Petition filed under Section 91 (1) (f) of the Electricity Act 2003 and Regulation 41 of the JSERC (Conduct of Business), Regulations 2016 seeking review of the Order dated 22.05.2023 passed by JSERC in Case (T) No. 02 of 2018 in the matter of True-up for FY 2016-17 and APR for FY 2017-18 in terms of provisions of the JSERC (Terms and Conditions for Determination of Generation Tariff), Regulations 2015 for supplying the regulated contracted capacity to JUVNL/JBVNL from 540 MW Coal based power plant of APNRL at Padapur and Srirampur villages in Seraikela Kharsawan District in the State of Jharkhand. 12.01.2024
1781 06 of 2023
M/s Usha Martin Limited Vrs. Jharkhand Urja Vikas Nigam Limited (JUVNL)
Petition purported to be filed under Regulation clause A10 (Dispute Resolution) and A11 (Power to Remove Difficulties) of JSERC (Utilization of surplus Capacity of Captive Power Plants based on conventional fuel) Regulations 2010 12.01.2024
1780 Miscellaneous Petition No. 05 of 2023
Jharkhand Bijli Vitran Nigam Limited
An affidavitated miscellaneous petition purported to be filed under Section 61, 86 and Section 181 of the Electricity Act 2003 for formulation of Regulatioin on installation and implementation of Prepaid Smart Metering in the State of Jharkhand 12.01.2024
1779 Case No. 16 of 2022
M/s Rungta Mines Ltd. Vrs. Jharkhand Urja Vikas Nigam Limited (JUVNL)
Petition filed under section 86 of the Electricity Act 2003 read alongwith Clause 10.6, 39.1 and 41.1 of the JSERC (Terms and Conditions for Intra State Open Access), Regulations 2016 seeking necessary directioin by upon the Distribution licensee namely, JBVNL to take necessary steps to consider the case of the petitoner for grant of no objection in connection with sale of power/energy in an open market regulated by CERC and administered by NOAR 12.01.2024
1778 23 of 2020 & Miscellaneous Petition No 01 of 2022
Jharkhand Small Industries Association (JSIA) Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Review of JSERC Tariff order for true up for FY 2018-19, Aggregate Revenue Requirement and Tariff for FY 2020-21 for JBVNL. 12.01.2024
1777 Case No.43 of 2023
M/s Tata Steel Utilities and Infrastructure Services Limited
For approval of Capital Expenditure for three schemes related to Network Extension/Augmentation and Reliability (Emergency requirement) 12.01.2024
1776 Case No. 01 of 2024
M/s Inland Power Limited (IPL) Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
For approval of draft 4th supplementary Power Purchase Agreement dated 23.02.2012 signed between JBVNL & M/s Inland Power Limited 12.01.2024
1775 Adjudicate Case No. 01 of 2023/Case No. 15 of 2023
The Bureau of Energy Efficiency Versus Jharkhand Bijli Vitran Nigam Limited
Petition filed under section 27 of the Energy Conservation Act, 2001 for adjudication of the penalty under Section 26 of the Energy Conservatin Act, 2001 by the Adujdication office and for directions to Jharkhand Bijli Vitran Nigam Limited to make payment as adjuicated by the Adjudicating officer. 09.01.2024
1774 Case No. 41 of 2023
Jharkhand Urja Sancharan Nigam Limited
Versus
Patratu Vidyut UtPatratu Vidyut Utpadan Nigam Limited (PVUNL)& Ors.
Petition in compliance of order dated 10.10.2023 and 03.11.2023 passed in case no.21 of 2023 for approval of evacuation of Power from Patratu Vidyut Utpadan Nigam Limited (PVUNL) 01.12.2023
1773 Case No.21 of 2023
Jharkhand Urja Sancharan Nigam Limited
Review of order dated 23.06.2023 for True up for FY 2019-20 and Business Plan & Multi Year Tariff for the Control Period FY 2021-22 to FY 2025-26 01.12.2023
1772 28 of 2023
Tata Steel Long Products Ltd. Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Direction upon the respondents to take a time bound decision upon the request made by the Petitioner seeking HT Industrial connection from the earlier CPP arrangement as contained in the letter dated 06.12.2022 effective from 01.07.2023 onwards for its steel plant at Gamharia. 01.12.2023
1771 37 of 2023
Pasari Steel Pvt. Ltd. Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Direction upon the Respondents to comply with the order dated 22.04.2008 passed by the learned CGRF, Ranchi in Case No.04/08 affirmed by the order dated 30.08.2008 passed by the Electricity Ombudsman in Case No. EOJ/17/2008 and to refund the amount with interest forthwith in so far ase in some cases amounts have already been released by adjusting the amount against KVA charges. 01.12.2023
1770 42 of 2023 Review of order dated 29.09.2023 for True up for FY 2020-21 and order dated 29.09.2023 for True up for 2021-22, APR for FY 2022-23 and ARR  & Tariff for FY 2023-24 01.12.2023
1769 40 of 2023
Swarnrekha Rice Mill Pvt. Ltd. Vrs. JBVNL & Ors.
Necessary approval of the Commission in taking new service H.T connection at supply voltage of of 33 KV having 800 KVA contract demand from JBVNL 01.12.2023
1768 38 of 2023
Steel Authority of India Ltd. Vrs. Damodar Valley Corporation
Petition filed under Section 94 (1) (f) of the Electricity Act, 2003 read with Regulation 41.1 of the JSERC (Conduct of Business) Regulations, 2016 for review of order dt. 12/06/2023 passed in Case No. 29 of 2020 along with application under section 5 of the limitation Act, 1963 for condonation of delay of 43 days is filing the review petition. 01.12.2023
1767 Case No. 16 of 2022
M/s Rungta Mines Ltd. Vrs. Jharkhand Urja Vikas Nigam Limited (JUVNL)
Petition filed under section 86 of the Electricity Act 2003 read alongwith Clause 10.6, 39.1 and 41.1 of the JSERC (Terms and Conditions for Intra State Open Access), Regulations 2016 seeking necessary directioin by upon the Distribution licensee namely, JBVNL to take necessary steps to consider the case of the petitoner for grant of no objection in connection with sale of power/energy in an open market regulated by CERC and administered by NOAR 01.12.2023
1766 06 of 2023
M/s Usha Martin Limited Vrs. Jharkhand Urja Vikas Nigam Limited (JUVNL)
Petition purported to be filed under Regulation clause A10 (Dispute Resolution) and A11 (Power to Remove Difficulties) of JSERC (Utilization of surplus Capacity of Captive Power Plants based on conventional fuel) Regulations 2010 01.12.2023
1765 Case No. 27 of 2023
 AMP Energy C & I Fifteen Private Limited Versus Jharkhand Urja Vikas Nigam Limited & Ors.
Petition under section 86 (1)(c) & (e) & (k) of the Electricity Act, 2003 read with regulation 55.3 of the Jharkhand State Electricity Regulatory Commission (Conduct of Business) Regulations, 2016 seeking appropriate reliefs/directions vis a vis the Jharkhand State Soloar Policy, 2022 for supply of solar power from its under developing captive solar project. 30.11.2023
1764 Case No. 05 of 2023
Damodar Valley Corporation (DVC)
Review of order dated 30.01.2023 passed in Case (T) no 01 of 2021 regarding determination of ARR for the MYT period from FY 2021-22 to 2025-26 and Tariff for FY 2021-22 30.11.2023
1763 Case No. 04 of 2023
Damodar Valley Corporation (DVC)
Review of order dated 30.01.2023 passed in Case (T) no. 11 of 2020 regarding True-up for FY 2019-20. 30.11.2023
1762 19 of 2023
Jharkhand Urja Sancharan Nigam Limited (JUSNL)
Review of order dated 12.06.2023 for True up for FY 2017-18 28.11.2023
1761 Adjudicate Case No. 01 of 2023/Case No. 15 of 2023
The Bureau of Energy Efficiency Versus Jharkhand Bijli Vitran Nigam Limited
Petition filed under section 27 of the Energy Conservation Act, 2001 for adjudication of the penalty under Section 26 of the Energy Conservatin Act, 2001 by the Adujdication office and for directions to Jharkhand Bijli Vitran Nigam Limited to make payment as adjuicated by the Adjudicating officer. 28.11.2023
1760 Case No. 41 of 2023
Jharkhand Urja Sancharan Nigam Limited
Versus
Patratu Vidyut UtPatratu Vidyut Utpadan Nigam Limited (PVUNL)& Ors.
Petition in compliance of order dated 10.10.2023 and 03.11.2023 passed in case no.21 of 2023 for approval of evacuation of Power from Patratu Vidyut Utpadan Nigam Limited (PVUNL) 28.11.2023
1759 Case No.21 of 2023
Jharkhand Urja Sancharan Nigam Limited
Review of order dated 23.06.2023 for True up for FY 2019-20 and Business Plan & Multi Year Tariff for the Control Period FY 2021-22 to FY 2025-26 28.11.2023
1758 Case No. 17 of 2023
Adhunik Power and Natural resources Ltd. (APNRL)
Versus
 Jharkhand Urja Vikas Nigam Limited & Ors.
Petition filed under Section 91 (1) (f) of the Electricity Act 2003 and Regulation 41 of the JSERC (Conduct of Business), Regulations 2016 seeking review of the Order dated 22.05.2023 passed by JSERC in Case (T) No. 02 of 2018 in the matter of True-up for FY 2016-17 and APR for FY 2017-18 in terms of provisions of the JSERC (Terms and Conditions for Determination of Generation Tariff), Regulations 2015 for supplying the regulated contracted capacity to JUVNL/JBVNL from 540 MW Coal based power plant of APNRL at Padapur and Srirampur villages in Seraikela Kharsawan District in the State of Jharkhand. 28.11.2023
1757 Miscellaneous Petition No. 05 of 2023
Jharkhand Bijli Vitran Nigam Limited
An affidavitated miscellaneous petition purported to be filed under Section 61, 86 and Section 181 of the Electricity Act 2003 for formulation of Regulatioin on installation and implementation of Prepaid Smart Metering in the State of Jharkhand 28.11.2023
1756 23 of 2023
 Inland Power Limited
For review of order dated 22.05.2023 regarding Truing up for FY 2020-21 of Inland Power Limited 24.11.2023
1755 25 of 2023
Aadhar Rice Mill Pvt. Ltd Vrs. Jharkhand Bijli Vitran Nigam Limited & Ors
Inter-alia for allowing the petitioner to take H.T connections from JBVNL at supply voltage of 33 KV having 600 KVA contract demand for Aadhar Rice Mill Pvt. Ltd. 22.11.2023
1754 23 of 2020 & Miscellaneous Petition No 01 of 2022
Jharkhand Small Industries Association (JSIA) Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Review of JSERC Tariff order for true up for FY 2018-19, Aggregate Revenue Requirement and Tariff for FY 2020-21 for JBVNL. 22.11.2023
1753 19 of 2022
M/s Auto Profiles Limited Vrs. JBVNL & Ors
Non-compliance of the judgement dated 19.02.2022 passed by the Consumer Grievance Redressal Forum, Chaibasa 22.11.2023
1752 36 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2020-21 17.11.2023
1751 35 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2019-20 17.11.2023
1750 34 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemptioin from RPO for FY 2018-19 17.11.2023
1749 33 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2017-18 17.11.2023
1748 32 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2016-17 17.11.2023
1747; 31 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2015-16 17.11.2023
1746 30 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2014-15 17.11.2023
1745 29 of 2023
Steel Authority of India Limited (SAIL) Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Subject - Exemption from RPO for FY 2013-14 17.11.2023
1744 28 of 2023
 Tata Steel Long Products Ltd. Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Direction upon the respondents to take a time bound decision upon the request made by the Petitioner seeking HT Industrial connection from the earlier CPP arrangement as contained in the letter dated 06.12.2022 effective from 01.07.2023 onwards for its steel plant at Gamharia. 17.11.2023
1743 Case No. 01 of 2022
SAIL, Bokaro Steel Plant
Versus
 Jharkhand Renewable Energy Development Agency (JREDA)
Petition purported to be filed under Regulations 13 read with 15.2 of the JSERC (Renewable Purchase Obligation and its compliance) Regulations, 2016 for exemption from RPO compliance for the period 2016-17, 2017-18, 2018-19, 2019-20, 2020-21 and further periods in terms of 2016 and 2021 (First amendment) Regulations. 17.11.2023
1742 Case No. 09 of 2019
M/s Vananchal Steel Alloys Private Limited Versus Damodar Valley Corporation & another
Order on Case No. 09 of 2019 17.11.2023
1741 Case No. 17 of 2022
Inland Power Limited (IPL) Vrs. Jharkhand Urja Vikas Nigam Limited & Ors.
Review of order dated 04th November 2022 for True up for FY 2019-20 17.11.2023
1740 37 of 2023
Pasari Steel Pvt. Ltd. Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Direction upon the Respondents to comply with the order dated 22.04.2008 passed by the learned CGRF, Ranchi in Case No.04/08 affirmed by the order dated 30.08.2008 passed by the Electricity Ombudsman in Case No. EOJ/17/2008 and to refund the amount with interest forthwith in so far ase in some cases amounts have already been released by adjusting the amount against KVA charges. 17.11.2023
1739 Case No. 28 of 2023
Tata Steel Long Products Ltd. Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Direction upon the respondents to take a time bound decision upon the request made by the Petitioner seeking HT Industrial connection from the earlier CPP arrangement as contained in the letter dated 06.12.2022 effective from 01.07.2023 onwards for its steel plant at Gamharia. 17.11.2023
1738 Case No. 41 of 2023
Jharkhand Urja Sancharan Nigam Limited
Versus
Patratu Vidyut UtPatratu Vidyut Utpadan Nigam Limited (PVUNL)& Ors.
Petition in compliance of order dated 10.10.2023 and 03.11.2023 passed in case no.21 of 2023 for approval of evacuation of Power from Patratu Vidyut Utpadan Nigam Limited (PVUNL) 10.11.2023
1737 39 of 2023
Jharkhand Urja Sancharan Nigam Limited (JUSNL)
Petition filed under clause 6.1 of the JSERC (Modalities of Tariff Determination) Regulations 2023 for approval of the Transmission project of the petitioner for providing quality power supply. 10.11.2023
1736 Case No.21 of 2023
Jharkhand Urja Sancharan Nigam Limited
Review of order dated 23.06.2023 for True up for FY 2019-20 and Business Plan & Multi Year Tariff for the Control Period FY 2021-22 to FY 2025-26 10.11.2023
1735 19 of 2023
Jharkhand Urja Sancharan Nigam Limited (JUSNL)
Review of order dated 12.06.2023 for True up for FY 2017-18 10.11.2023
1734 25 of 2023
Aadhar Rice Mill Pvt. Ltd Vrs. Jharkhand Bijli Vitran Nigam Limited & Ors
Inter-alia for allowing the petitioner to take H.T connections from JBVNL at supply voltage of 33 KV having 600 KVA contract demand for Aadhar Rice Mill Pvt. Ltd. 10.11.2023
1733 23 of 2023
 Inland Power Limited
For review of order dated 22.05.2023 regarding Truing up for FY 2020-21 of Inland Power Limited 10.11.2023
1732 19 of 2022
M/s Auto Profiles Limited Vrs. JBVNL & Ors
Non-compliance of the judgement dated 19.02.2022 passed by the Consumer Grievance Redressal Forum, Chaibasa 10.11.2023
1731 Case No. 17 of 2023
Adhunik Power and Natural resources Ltd. (APNRL)
Versus
 Jharkhand Urja Vikas Nigam Limited & Ors.
Petition filed under Section 91 (1) (f) of the Electricity Act 2003 and Regulation 41 of the JSERC (Conduct of Business), Regulations 2016 seeking review of the Order dated 22.05.2023 passed by JSERC in Case (T) No. 02 of 2018 in the matter of True-up for FY 2016-17 and APR for FY 2017-18 in terms of provisions of the JSERC (Terms and Conditions for Determination of Generation Tariff), Regulations 2015 for supplying the regulated contracted capacity to JUVNL/JBVNL from 540 MW Coal based power plant of APNRL at Padapur and Srirampur villages in Seraikela Kharsawan District in the State of Jharkhand. 10.11.2023
1730 23 of 2020 & Miscellaneous Petition No 01 of 2022
Jharkhand Small Industries Association (JSIA) Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Petition purported to filed under Regulation 42 and 45 of JSERC (Conduct of Business) Regulations, 2016 challenging the maintainability of the Review petition being case no. 23 of of 2020 filed by JBVNL, which is filed under Section 94 of the Electricity Act 2003 and Regulations 41 (1) (2) & (3) of the JSERC (Conduct of Business) Regulations, 2016 for review of JSERC Tariff order for true up for FY 2018-19, Aggregate Revenue Requirement and Tariff for FY 2020-21 for JBVNL. 10.11.2023
1729 Miscellaneous Petition No. 05 of 2023
Jharkhand Bijli Vitran Nigam Limited
An affidavitated miscellaneous petition purported to be filed under Section 61, 86 and Section 181 of the Electricity Act 2003 for formulation of Regulatioin on installation and implementation of Prepaid Smart Metering in the State of Jharkhand 10.11.2023
1728 Case No. 04 of 2020
 M/s Gautam Ferro Alloys Vrs. Jharkhand Bijli Vitran Nigam Ltd. & Ors.
Order on Case No. 04 of 2020 10.11.2023
1727 39 of 2023
Jharkhand Urja Sancharan Nigam Limited (JUSNL)
Petition filed under clause 6.1 of the JSERC (Modalities of Tariff Determination) Regulations 2023 for approval of the Transmission project of the petitioner for providing quality power supply. 09.11.2023
1726 Case No.21 of 2023
Jharkhand Urja Sancharan Nigam Limited
Review of order dated 23.06.2023 for True up for FY 2019-20 and Business Plan & Multi Year Tariff for the Control Period FY 2021-22 to FY 2025-26 09.11.2023
1725 19 of 2023
Jharkhand Urja Sancharan Nigam Limited (JUSNL)
Review of order dated 12.06.2023 for True up for FY 2017-18 09.11.2023
1724 Case No. 41 of 2023
Jharkhand Urja Sancharan Nigam Limited
Versus
Patratu Vidyut UtPatratu Vidyut Utpadan Nigam Limited (PVUNL)& Ors.
Petition in compliance of order dated 10.10.2023 and 03.11.2023 passed in case no.21 of 2023 for approval of evacuation of Power from Patratu Vidyut Utpadan Nigam Limited (PVUNL) 09.11.2023
1723 38 of 2023
Steel Authority of India Ltd. Vrs. Damodar Valley Corporation
Petition filed under Section 94 (1) (f) of the Electricity Act, 2003 read with Regulation 41.1 of the JSERC (Conduct of Business) Regulations, 2016 for review of order dt. 12/06/2023 passed in Case No. 29 of 2020 along with application under section 5 of the limitation Act, 1963 for condonation of delay of 43 days is filing the review petition. 03.11.2023
1722 39 of 2023
Jharkhand Urja Sancharan Nigam Limited (JUSNL)
Petition filed under clause 6.1 of the JSERC (Modalities of Tariff Determination) Regulations 2023 for approval of the Transmission project of the petitioner for providing quality power supply. 03.11.2023
1721 40 of 2023
Swarnrekha Rice Mill Pvt. Ltd. Vrs. JBVNL & Ors.
Necessary approval of the Commission in taking new service H.T connection at supply voltage of of 33 KV having 800 KVA contract demand from JBVNL 03.11.2023
1720 Case No.21 of 2023
Jharkhand Urja Sancharan Nigam Limited
Review of order dated 23.06.2023 for True up for FY 2019-20 and Business Plan & Multi Year Tariff for the Control Period FY 2021-22 to FY 2025-26 03.11.2023
1719 Case No. 16 of 2022
M/s Rungta Mines Ltd. Vrs. Jharkhand Urja Vikas Nigam Limited (JUVNL)
Petition filed under section 86 of the Electricity Act 2003 read alongwith Clause 10.6, 39.1 and 41.1 of the JSERC (Terms and Conditions for Intra State Open Access), Regulations 2016 seeking necessary directioin by upon the Distribution licensee namely, JBVNL to take necessary steps to consider the case of the petitoner for grant of no objection in connection with sale of power/energy in an open market regulated by CERC and administered by NOAR 03.11.2023
1718 06 of 2023
M/s Usha Martin Limited Vrs. Jharkhand Urja Vikas Nigam Limited (JUVNL)
Petition purported to be filed under Regulation clause A10 (Dispute Resolution) and A11 (Power to Remove Difficulties) of JSERC (Utilization of surplus Capacity of Captive Power Plants based on conventional fuel) Regulations 2010 03.11.2023
1717 19 of 2023
Jharkhand Urja Sancharan Nigam Limited (JUSNL)
Review of order dated 12.06.2023 for True up for FY 2017-18 03.11.2023
1716 Case No. 23 of 2020
& MP No. 01 of 2022
Review petition on the order dated 01.10.2020 in Case (T) No. 13 of 2019 on the petition for true up for FY 2018-19, APR for FY 2019-20 and ARR Tariff for FY 2020-21 02.11.2023
1715 Case No.  05 of 2023
Damodar Valley Corporation (DVC)
Review of order dated 30.01.2023 passed in Case (T) no 01 of 2021 regarding determinatin of ARR for the MYT period from FY 2021-22 to 2025-26 and Tariff for FY 2021-22 02.11.2023
1714 Case No. 04 of 2023
Damodar Valley Corporation (DVC)
Review of order dated 30.01.2023 passed in Case (T) no. 11 of 2020 regarding True-up for FY 2019-20. 02.11.2023
1713 19 of 2022
M/s Auto Profiles Limited Vrs. JBVNL & Ors
Non-compliance of the judgement dated 19.02.2022 passed by the Consumer Grievance Redressal Forum, Chaibasa 02.11.2023
1712 Case No. 15 of 2023
The Bureau of Energy Efficiency Versus Jharkhand Bijli Vitran Nigam Limited
Petition filed under section 27 of the Energy Conservation Act, 2001 for adjudication of the penalty under Section 26 of the Energy Conservatin Act, 2001 by the Adujdication office and for directions to Jharkhand Bijli Vitran Nigam Limited to make payment as adjuicated by the Adjudicating officer. 31.10.2023
1711 Case No. 17 of 2023
Adhunik Power and Natural resources Ltd. (APNRL)
Versus
 Jharkhand Urja Vikas Nigam Limited & Ors.
Petition filed under Section 91 (1) (f) of the Electricity Act 2003 and Regulation 41 of the JSERC (Conduct of Business), Regulations 2016 seeking review of the Order dated 22.05.2023 passed by JSERC in Case (T) No. 02 of 2018 in the matter of True-up for FY 2016-17 and APR for FY 2017-18 in terms of provisions of the JSERC (Terms and Conditions for Determination of Generation Tariff), Regulations 2015 for supplying the regulated contracted capacity to JUVNL/JBVNL from 540 MW Coal based power plant of APNRL at Padapur and Srirampur villages in Seraikela Kharsawan District in the State of Jharkhand. 10.10.2023
1710 Case No. 16 of 2022
M/s Rungta Mines Ltd. Vrs. Jharkhand Urja Vikas Nigam Limited (JUVNL)
Petition filed under section 86 of the Electricity Act 2003 read alongwith Clause 10.6, 39.1 and 41.1 of the JSERC (Terms and Conditions for Intra State Open Access), Regulations 2016 seeking necessary directioin by upon the Distribution licensee namely, JBVNL to take necessary steps to consider the case of the petitoner for grant of no objection in connection with sale of power/energy in an open market regulated by CERC and administered by NOAR 10.10.2023
1709 37 of 2023
Pasari Steel Pvt. Ltd. Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Petition purported to be filed under clause 26 of JSERC (Guidelines for establishent of Forum for Redressal of Grievances of the Consumers and Electricity Ombudsman) Regulations, 2011 for a direction upon the Respondents to comply with the order dated 22.04.2008 passed by the learned CGRF, Ranchi in Case No.04/08 affirmed by the order dated 30.08.2008 passed by the Electricity Ombudsman in Case No. EOJ/17/2008 and to refund the amount with interest forthwith in so far ase in some cases amounts have already been released by adjusting the amount against KVA charges. 10.10.2023
1708 23 of 2020 & Miscellaneous Petition No 01 of 2022
Jharkhand Small Industries Association (JSIA) Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Petition purported to filed under Regulation 42 and 45 of JSERC (Conduct of Business) Regulations, 2016 challenging the maintainability of the Review petition being case no. 23 of of 2020 filed by JBVNL, which is filed under Section 94 of the Electricity Act 2003 and Regulations 41 (1) (2) & (3) of the JSERC (Conduct of Business) Regulations, 2016 for review of JSERC Tariff order for true up for FY 2018-19, Aggregate Revenue Requirement and Tariff for FY 2020-21 for JBVNL. 10.10.2023
1707 Miscellaneous Petition No. 05 of 2023
Jharkhand Bijli Vitran Nigam Limited
An affidavitated miscellaneous petition purported to be filed under Section 61, 86 and Section 181 of the Electricity Act 2003 for formulation of Regulatioin on installation and implementation of Prepaid Smart Metering in the State of Jharkhand 10.10.2023
1706 26 of 2023
Jharkhand Bijli Vitran Nigam Limited Vrs. Tenughat Vidyut Nigam Limited
Petition purported to be filed under clause 6.29 of JSERC (Term and Conditions for Determination of Distribution Tariff) Regulations 2020 for approval of Power Purchase Agreement (PPA) between Jharkhand Bijli Vitran Nigam Limited and Tenughat Vidyut Nigam Limited for purchase of 420 MW at the rate determined by JSERC for period of 10 (Ten) years. 10.10.2023
1705 Case No.21 of 2023
Jharkhand Urja Sancharan Nigam Limited
Review of order dated 23.06.2023 for True up for FY 2019-20 and Business Plan & Multi Year Tariff for the Control Period FY 2021-22 to FY 2025-26 10.10.2023
1704 37 of 2023
Pasari Steel Pvt. Ltd. Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Petition purported to be filed under clause 26 of JSERC (Guidelines for establishent of Forum for Redressal of Grievances of the Consumers and Electricity Ombudsman) Regulations, 2011 for a direction upon the Respondents to comply with the order dated 22.04.2008 passed by the learned CGRF, Ranchi in Case No.04/08 affirmed by the order dated 30.08.2008 passed by the Electricity Ombudsman in Case No. EOJ/17/2008 and to refund the amount with interest forthwith in so far ase in some cases amounts have already been released by adjusting the amount against KVA charges. 06.10.2023
1703 06 of 2023
M/s Usha Martin Limited Vrs. Jharkhand Urja Vikas Nigam Limited (JUVNL)
Petition purported to be filed under Regulation clause A10 (Dispute Resolution) and A11 (Power to Remove Difficulties) of JSERC (Utilization of surplus Capacity of Captive Power Plants based on conventional fuel) Regulations 2010 06.10.2023
1702 23 of 2020 & Miscellaneous Petition No 01 of 2022
Jharkhand Small Industries Association (JSIA) Vrs. Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Petition purported to filed under Regulation 42 and 45 of JSERC (Conduct of Business) Regulations, 2016 challenging the maintainability of the Review petition being case no. 23 of of 2020 filed by JBVNL, which is filed under Section 94 of the Electricity Act 2003 and Regulations 41 (1) (2) & (3) of the JSERC (Conduct of Business) Regulations, 2016 for review of JSERC Tariff order for true up for FY 2018-19, Aggregate Revenue Requirement and Tariff for FY 2020-21 for JBVNL. 06.10.2023
1701 Miscellaneous Petition No. 05 of 2023
Jharkhand Bijli Vitran Nigam Limited
An affidavitated miscellaneous petition purported to be filed under Section 61, 86 and Section 181 of the Electricity Act 2003 for formulation of Regulatioin on installation and implementation of Prepaid Smart Metering in the State of Jharkhand 06.10.2023
1700 26 of 2023
Jharkhand Bijli Vitran Nigam Limited Vrs. Tenughat Vidyut Nigam Limited
Petition purported to be filed under clause 6.29 of JSERC (Term and Conditions for Determination of Distribution Tariff) Regulations 2020 for approval of Power Purchase Agreement (PPA) between Jharkhand Bijli Vitran Nigam Limited and Tenughat Vidyut Nigam Limited for purchase of 420 MW at the rate determined by JSERC for period of 10 (Ten) years. 06.10.2023
1699 Case No.21 of 2023
Jharkhand Urja Sancharan Nigam Limited
Review of order dated 23.06.2023 for True up for FY 2019-20 and Business Plan & Multi Year Tariff for the Control Period FY 2021-22 to FY 2025-26 06.10.2023
1698 19 of 2023
Jharkhand Urja Sancharan Nigam Limited (JUSNL)
Review of order dated 12.06.2023 for True up for FY 2017-18 06.10.2023
1697 Case No. 16 of 2022
M/s Rungta Mines Ltd. Vrs. Jharkhand Urja Vikas Nigam Limited (JUVNL)
Petition filed under section 86 of the Electricity Act 2003 read alongwith Clause 10.6, 39.1 and 41.1 of the JSERC (Terms and Conditions for Intra State Open Access), Regulations 2016 seeking necessary directioin by upon the Distribution licensee namely, JBVNL to take necessary steps to consider the case of the petitoner for grant of no objection in connection with sale of power/energy in an open market regulated by CERC and administered by NOAR 06.10.2023
1696 04 of 2023
DVC Vrs. Association of the DVC HT Consumer of Jharkhand
Review of order dated 30.01.2023 passed in Case (T) no. 11 of 2020 regarding True-up for FY 2019-20. 03.10.2023
1695 05 of 2023
Damodar Valley Corporation (DVC)
Review of order dated 30.01.2023 passed in Case (T) no 01 of 2021 regarding determinatin of ARR for the MYT period from FY 2021-22 to 2025-26 and Tariff for FY 2021-22 03.10.2023
1694 Case No. 17 of 2023
Adhunik Power and Natural resources Ltd. (APNRL)
Versus
 Jharkhand Urja Vikas Nigam Limited & Ors.
Petition filed under Section 91 (1) (f) of the Electricity Act 2003 and Regulation 41 of the JSERC (Conduct of Business), Regulations 2016 seeking review of the Order dated 22.05.2023 passed by JSERC in Case (T) No. 02 of 2018 in the matter of True-up for FY 2016-17 and APR for FY 2017-18 in terms of provisions of the JSERC (Terms and Conditions for Determination of Generation Tariff), Regulations 2015 for supplying the regulated contracted capacity to JUVNL/JBVNL from 540 MW Coal based power plant of APNRL at Padapur and Srirampur villages in Seraikela Kharsawan District in the State of Jharkhand. 26.09.2023
1693 19 of 2022
M/s Auto Profiles Limited Vrs. JBVNL & Ors
Non-compliance of the judgement dated 19.02.2022 passed by the Consumer Grievance Redressal Forum, Chaibasa 26.09.2023
1692 25 of 2023
Aadhar Rice Mill Pvt. Ltd Vrs. Jharkhand Bijli Vitran Nigam Limited & Ors
Inter-alia for allowing the petitioner to take H.T connections from JBVNL at supply voltage of 33 KV having 600 KVA contract demand for Aadhar Rice Mill Pvt. Ltd. 26.09.2023
1691 23 of 2023
 Inland Power Limited
For review of order dated 22.05.2023 regarding Truing up for FY 2020-21 of Inland Power Limited 26.09.2023
1690 Case No. 16 of 2022
M/s Rungta Mines Ltd. Vrs. Jharkhand Urja Vikas Nigam Limited (JUVNL)
Petition filed under section 86 of the Electricity Act 2003 read alongwith Clause 10.6, 39.1 and 41.1 of the JSERC (Terms and Conditions for Intra State Open Access), Regulations 2016 seeking necessary directioin by upon the Distribution licensee namely, JBVNL to take necessary steps to consider the case of the petitoner for grant of no objection in connection with sale of power/energy in an open market regulated by CERC and administered by NOAR 26.09.2023
1689 Case No.  05 of 2023
Damodar Valley Corporation (DVC)
Review of order dated 30.01.2023 passed in Case (T) no 01 of 2021 regarding determinatin of ARR for the MYT period from FY 2021-22 to 2025-26 and Tariff for FY 2021-22 26.09.2023
1688 Case No. 04 of 2023
Damodar Valley Corporation (DVC)
Review of order dated 30.01.2023 passed in Case (T) no. 11 of 2020 regarding True-up for FY 2019-20. 26.09.2023
1687 Case No. 04 of 2020
 M/s Gautam Ferro Alloys Vrs. Jharkhand Bijli Vitran Nigam Ltd. & Ors.
Order on Case No. 04 of 2020 26.09.2023
1686 Case No. 15 of 2023
The Bureau of Energy Efficiency Versus Jharkhand Bijli Vitran Nigam Limited
Petition filed under section 27 of the Energy Conservation Act, 2001 for adjudication of the penalty under Section 26 of the Energy Conservatin Act, 2001 by the Adujdication office and for directions to Jharkhand Bijli Vitran Nigam Limited to make payment as adjuicated by the Adjudicating officer. 21.09.2023
1685 Case No. 06 of 2023
Association of DVC HT Consumers of Jharkhand Vrs. Damodar Valley Corporation (DVC)
Submission of Review petition pertaining to revision of voltage rebate and subsequent issue of corrigendum against the Tariff order for Distribution Activity of Damodar Valley Corporation (DVC) in Jharkhand State- True up for FY 2018-19, APR for FY 2019-20 and ARR & Tariff for FY 2020-21 dated 30.09.2020 issued by Hon'ble JSERC 12.09.2023
1684 Case No. 01 of 2022
SAIL, Bokaro Steel Plant
Versus
 Jharkhand Renewable Energy Development Agency (JREDA)
Petition purported to be filed under Regulations 13 read with 15.2 of the JSERC (Renewable Purchase Obligation and its compliance) Regulations, 2016 for exemption from RPO compliance for the period 2016-17, 2017-18, 2018-19, 2019-20, 2020-21 and further periods in terms of 2016 and 2021 (First amendment) Regulations. 12.09.2023
1683 Case No. 17 of 2022
Inland Power Limited (IPL) Vrs. Jharkhand Urja Vikas Nigam Limited & Ors.
Review of order dated 04th November 2022 for True up for FY 2019-20 12.09.2023
1682 Case No. 23 of 2020
& MP No. 01 of 2022
Review petition on the order dated 01.10.2020 in Case (T) No. 13 of 2019 on the petition for true up for FY 2018-19, APR for FY 2019-20 and ARR Tariff for FY 2020-21 12.09.2023
1681 09 of 2019
M/s Vananchal Steel Alloys (Pvt.) Ltd. Versus Damodar Valley Corporation (DVC) & Anr
Order on Case No. 09 of 2019 12.09.2023
1680 Case No. 27 of 2023
 AMP Energy C & I Fifteen Private Limited Versus Jharkhand Urja Vikas Nigam Limited & Ors.
Petition under section 86 (1)(c) & (e) & (k) of the Electricity Act, 2003 read with regulation 55.3 of the Jharkhand State Electricity Regulatory Commission (Conduct of Business) Regulations, 2016 seeking appropriate reliefs/directions vis a vis the Jharkhand State Soloar Policy, 2022 for supply of solar power from its under developing captive solar project. 12.09.2023
1679 17 of 2023
Adhunik Power and Natural Resources Limited Vrs. Jharkhand Urja Vikas Nigam Limited & Ors.
Petition filed under Section 91 (1) (f) of the Electricity Act 2003 and Regulation 41 of the JSERC (Conduct of Business), Regulations 2016 seeking review of the Order dated 22.05.2023 passed by JSERC in Case (T) No. 02 of 2018 in the matter of True-up for FY 2016-17 and APR for FY 2017-18 in terms of provisions of the JSERC (Terms and Conditions for Determination of Generation Tariff), Regulations 2015 for supplying the regulated contracted capacity to JUVNL/JBVNL from 540 MW Coal based power plant of APNRL at Padapur and Srirampur villages in Seraikela Kharsawan District in the State of Jharkhand. 29.08.2023
1678 19 of 2022
M/s Auto Profiles Limited Vrs. JBVNL & Ors
Non-compliance of the judgement dated 19.02.2022 passed by the Consumer Grievance Redressal Forum, Chaibasa 29.08.2023
1677 Case No.30 of 2020
Tata Steel Limited (TSL)
 Vrs.
 Damodar Valley Corporation (DVC)
Order on Case No. 30 of 2020 28.08.2023
1676 Case No.30 of 2020
Tata Steel Limited (TSL)
 Vrs.
 Damodar Valley Corporation (DVC)
Order on Case No. 30 of 2020 22.08.2023
1675 Case No.21 of 2023
Jharkhand Urja Sancharan Nigam Limited
Review of order dated 23.06.2023 for True up for FY 2019-20 and Business Plan & Multi Year Tariff for the Control Period FY 2021-22 to FY 2025-26 18.08.2023
1674 Case No. 15 of 2023
The Bureau of Energy Efficiency Versus Jharkhand Bijli Vitran Nigam Limited
Petition filed under section 27 of the Energy Conservation Act, 2001 for adjudication of the penalty under Section 26 of the Energy Conservatin Act, 2001 by the Adujdication office and for directions to Jharkhand Bijli Vitran Nigam Limited to make payment as adjuicated by the Adjudicating officer. 18.08.2023
1672 09 of 2023
Jharkhand Bijli Vitran Nigam Limited (JBVNL) Vrs. Solar Energy Corporation of India Limited (SECI), New Delhi
For approval of provisional Power Purchase Agreement (PPA) between Jharkhand Bijli Vitran Nigam Limited and Solar Energy Corporation of India Limited (SECI) for purchase of 100 MW floating solar power to be installed at Getalsud Dam by Solar Energy Corporation of India Limited (SECI) 18.08.2023
1671 07 of 2023
 M/s Sigma HTS LLP Vrs. Tata Steel Utilities and Infrastructure Services Ltd.
Petition purported to be filed under section 62 (5) and (6) read with section 129 of the Electricity Act, 2003 inter-alia for issuance of a direction to TSUISL to grant appropriate voltage rebate in terms of tariff order 2021-22 published on 24.11.2022 effective from 01.12.2022 18.08.2023
1670 Case No.30 of 2020
Tata Steel Limited (TSL)
 Vrs.
 Damodar Valley Corporation (DVC)
Order on Case No. 30 of 2020 18.08.2023
1669 Case No.30 of 2020
Tata Steel Limited (TSL)
 Vrs.
 Damodar Valley Corporation (DVC)
Order on Case No. 30 of 2020 11.08.2023
1668 Case No. 17 of 2023
Adhunik Power and Natural resources Ltd. (APNRL)
Versus
 Jharkhand Urja Vikas Nigam Limited & Ors.
Petition filed under Section 91 (1) (f) of the Electricity Act 2003 and Regulation 41 of the JSERC (Conduct of Business), Regulations 2016 seeking review of the Order dated 22.05.2023 passed by JSERC in Case (T) No. 02 of 2018 in the matter of True-up for FY 2016-17 and APR for FY 2017-18 in terms of provisions of the JSERC (Terms and Conditions for Determination of Generation Tariff), Regulations 2015 for supplying the regulated contracted capacity to JUVNL/JBVNL from 540 MW Coal based power plant of APNRL at Padapur and Srirampur villages in Seraikela Kharsawan District in the State of Jharkhand. 04.08.2023
1667 Case No.  05 of 2023
Damodar Valley Corporation (DVC)
Review of order dated 30.01.2023 passed in Case (T) no 01 of 2021 regarding determinatin of ARR for the MYT period from FY 2021-22 to 2025-26 and Tariff for FY 2021-22 04.08.2023
1666 Case No. 04 of 2023
Damodar Valley Corporation (DVC)
Review of order dated 30.01.2023 passed in Case (T) no. 11 of 2020 regarding True-up for FY 2019-20. 04.08.2023
1665 13 of 2023
 Tenughat Vidyut Nigam Limited (TVNL)
Petition purported to be filed under JSERC (Terms and Conditions for Determination of Generation Tariff) Regulations 2020 inter-alia in the clauses of Return on Equity as well as for alignment of depreciation rates as prescribed by Honble Central Electricity Regulatory Commision (CERC) 04.08.2023
1664 12 of 2023
Tata Power Company Limited (TPCL)
Petition purported to be filed under clause 32 & 33 of the JSERC (Terms and Conditions for Determination of Generation Tariff) Regulations 2020 read with clause 45 of the JSERC (Conduct of Business ) Regulations 2016 as well as Section 79(1) (b) of the Electricity Act 2003 seeking removal of difficulties/modification/amendment/review of provisions of JSERC (Terms and Conditions for Determination of Generation Tariff) Regulations, 2020. 04.08.2023
1663 Case No. 03 of 2023
Inland Power Limited
Petition for seeking amendment of the JSERC (Terms & Condition for determination of Generation Tariff) Regulation, 2020 under section 61 of the Electricity Act 2003 04.08.2023
1662 19 of 2022
M/s Auto Profiles Ltd. Versus Jharkhand Bijli Vitran Nigam Ltd. &Ors.
Non-compliance of the judgement dated 19.02.2022 passed by the Consumer Grievance Redressal Forum, Chaibasa 04.08.2023
1661 Case No. 16 of 2022
M/s Rungta Mines Ltd. Vrs. Jharkhand Urja Vikas Nigam Limited (JUVNL)
Petition filed under section 86 of the Electricity Act 2003 read alongwith Clause 10.6, 39.1 and 41.1 of the JSERC (Terms and Conditions for Intra State Open Access), Regulations 2016 seeking necessary directioin by upon the Distribution licensee namely, JBVNL to take necessary steps to consider the case of the petitoner for grant of no objection in connection with sale of power/energy in an open market regulated by CERC and administered by NOAR 04.08.2023
1660 01 of 2022
SAIL, Bokaro Steel Plant Vrs. Jharkhand Renewable Energy Development Agency (JREDA)
Petition purported to be filed under Regulations 13 read 15.2 of the JSERC (Renewable Purchas Obligation and its compliance) Regulations 2016 for exemption from RPO compliance for the period 2016-17, 2017-18, 2018-19, 2019-20, 2020-21 and further periods in terms of 2016 and 2021 (First amendment) Regulations. 04.08.2023
1659 Miscellaneous Petition No. 04 of 2023
Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Petition for taking into consideration the milestones/deadlines set by the Revamped Distribution Sector Scheme (RDSS) 04.08.2023
1658 19 of 2023
Jharkhand Urja Sancharan Nigam Limited (JUSNL)
Review of order dated 12.06.2023 for True up for FY 2017-18 04.08.2023
1657 18 of 2023
Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Review of order dated 31.05.2023 passed in Case (T) 04 of 2020 for Trueup for FY 2019-20, Annual Performance Review for FY 2020-21 and Business Plan & MYT for control period from FY 2021-22 to FY 2025-26 and Tariff for FY 2021-22 04.08.2023
1656 09 of 2023
Jharkhand Bijli Vitran Nigam Limited (JBVNL) Vrs. Solar Energy Corporation of India Limited (SECI), New Delhi
For approval of provisional Power Purchase Agreement (PPA) between Jharkhand Bijli Vitran Nigam Limited and Solar Energy Corporation of India Limited (SECI) for purchase of 100 MW floating solar power to be installed at Getalsud Dam by Solar Energy Corporation of India Limited (SECI) 03.08.2023
1655 Case No. 23 of 2020
& MP No. 01 of 2022
Review petition on the order dated 01.10.2020 in Case (T) No. 13 of 2019 on the petition for true up for FY 2018-19, APR for FY 2019-20 and ARR Tariff for FY 2020-21 02.08.2023
1654 Case No. 04 of 2020
 M/s Gautam Ferro Alloys Vrs. Jharkhand Bijli Vitran Nigam Ltd. & Ors.
Order on Case No. 04 of 2020 02.08.2023
1653 11 of 2023
 Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Petition purported to be filed under JSERC (Rooftop Solar PV Grid Interactive Systems and Net/Gross Metering) Regulations, 2015 inter-alia for amendment of maximum peak capaciity of the grid connected rooftop solar PV system to be installed by any eligible consumer or third party owner. 01.08.2023
1652 09 of 2019
M/s Vananchal Steel Alloys (Pvt.) Ltd. Versus Damodar Valley Corporation (DVC) & Anr
Order on Case No. 09 of 2019 01.08.2023
1651 Case No. 10 of 2023
 M/s Dilip Buildcon Limited Vrs. Jharkhand Bijli Vitran Nigam Limited
Petition purported under clause 4.7 of the (Electricity Supply Code), Regulations, 2015 inter-alia for allowing the petitioner to take new connection from JBVNL at supply voltage of 33 KV having 1000 KVA contract demand. 01.08.2023
1650 Case No. 02 of 2023
Damodar Valley Corporation
Versus
 Association of DVC HT Consumers of Jharkhand
Damodar Valley Corporation (DVC) has submitted an affidavited petition purported to be filled under section 61 and 62 of the Electricity Act, 2003 read with Regulations 22.1 of JSERC (Terms and Conditions for Determination of Distribution Tariff) Regulations 2020 for amendment of clause 10.7 of JSERC (Terms and conditions for Determination of distribution Tariff) Regulations 2020 by which celling/capping of 10% variable component has been made for the recovery of FPPPA for the part of the Damodar Valley area falling within the territory of the state of Jharkhand. 01.08.2023
1649 08 of 2023
Damodar Valley Corporation
Petition purported to be filed under section 62,64 & 86 of the Electricity Act, 2003 read with the applicable provisions of the DVC Act 1948, interalia for approval towards investment for creations of necessary infrastruture to provide supply of electricity to 11 KV Consumer in the state of Jharkhand by Damodar Valley Cororation in accordance with Regulation 6.12 of JSERC (Terms and Conditions for Determination of Distribution Tariff) Regulations 2020 as amended. 01.08.2023
1648 07 of 2023
 M/s Sigma HTS LLP Vrs. Tata Steel Utilities and Infrastructure Services Ltd.
Petition purported to be filed under section 62 (5) and (6) read with section 129 of the Electricity Act, 2003 inter-alia for issuance of a direction to TSUISL to grant appropriate voltage rebate in terms of tariff order 2021-22 published on 24.11.2022 effective from 01.12.2022 01.08.2023
1647 Case No. 06 of 2023
Association of DVC HT Consumers of Jharkhand Vrs. Damodar Valley Corporation (DVC)
Submission of Review petition pertaining to revision of voltage rebate and subsequent issue of corrigendum against the Tariff order for Distribution Activity of Damodar Valley Corporation (DVC) in Jharkhand State- True up for FY 2018-19, APR for FY 2019-20 and ARR & Tariff for FY 2020-21 dated 30.09.2020 issued by Hon'ble JSERC 01.08.2023
1646 Case No. 17 of 2022
Inland Power Limited (IPL) Vrs. Jharkhand Urja Vikas Nigam Limited & Ors.
Review of order dated 04th November 2022 for True up for FY 2019-20 01.08.2023
1645 19 of 2022
M/s Auto Profiles Ltd. Versus Jharkhand Bijli Vitran Nigam Ltd. &Ors.
Non-compliance of the judgement dated 19.02.2022 passed by the Consumer Grievance Redressal Forum, Chaibasa 14.07.2023
1644 13 of 2023
 Tenughat Vidyut Nigam Limited (TVNL)
Petition purported to be filed under JSERC (Terms and Conditions for Determination of Generation Tariff) Regulations 2020 inter-alia in the clauses of Return on Equity as well as for alignment of depreciation rates as prescribed by Honble Central Electricity Regulatory Commision (CERC) 14.07.2023
1643 12 of 2023
Tata Power Company Limited (TPCL)
Petition purported to be filed under clause 32 & 33 of the JSERC (Terms and Conditions for Determination of Generation Tariff) Regulations 2020 read with clause 45 of the JSERC (Conduct of Business ) Regulations 2016 as well as Section 79(1) (b) of the Electricity Act 2003 seeking removal of difficulties/modification/amendment/review of provisions of JSERC (Terms and Conditions for Determination of Generation Tariff) Regulations, 2020. 14.07.2023
1642 Case No. 03 of 2023
Inland Power Limited
Petition for seeking amendment of the JSERC (Terms & Condition for determination of Generation Tariff) Regulation, 2020 under section 61 of the Electricity Act 2003 14.07.2023
1641 Case No. 17 of 2023
Adhunik Power and Natural resources Ltd. (APNRL)
Versus
 Jharkhand Urja Vikas Nigam Limited & Ors.
Petition filed under Section 91 (1) (f) of the Electricity Act 2003 and Regulation 41 of the JSERC (Conduct of Business), Regulations 2016 seeking review of the Order dated 22.05.2023 passed by JSERC in Case (T) No. 02 of 2018 in the matter of True-up for FY 2016-17 and APR for FY 2017-18 in terms of provisions of the JSERC (Terms and Conditions for Determination of Generation Tariff), Regulations 2015 for supplying the regulated contracted capacity to JUVNL/JBVNL from 540 MW Coal based power plant of APNRL at Padapur and Srirampur villages in Seraikela Kharsawan District in the State of Jharkhand. 14.07.2023
1640 Case No. 16 of 2023
Tata Steel Limited (TSL)
Petition filed under section A44 of the JSERC (Conduct of Business ) Regulation 2016 for approval of Capital Expenditure for capacity augmentation of 400/132 KV Bulk Power Receiving Substation (BPRS) at Jamshedpur. 14.07.2023
1639 Case No. 15 of 2023
The Bureau of Energy Efficiency Versus Jharkhand Bijli Vitran Nigam Limited
Petition filed under section 27 of the Energy Conservation Act, 2001 for adjudication of the penalty under Section 26 of the Energy Conservatin Act, 2001 by the Adujdication office and for directions to Jharkhand Bijli Vitran Nigam Limited to make payment as adjuicated by the Adjudicating officer. 14.07.2023
1638 Case No.09 of 2019
M/s Vananchal Steel Alloys (Pvt.) Ltd. Versus Damodar Valley Corporation (DVC) & Anr
Order on Case No. 09 of 2019 11.07.2023
1637 Case 11 of 2023
Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Petition purported to be filed under JSERC (Rooftop Solar PV Grid Interactive Systems and Net/Gross Metering) Regulations, 2015 inter-alia for amendment of maximum peak capaciity of the grid connected rooftop solar PV system to be installed by any eligible consumer or third party owner. 11.07.2023
1636 Case No. 10 of 2023
 M/s Dilip Buildcon Limited Vrs. Jharkhand Bijli Vitran Nigam Limited
Petition purported under clause 4.7 of the (Electricity Supply Code), Regulations, 2015 inter-alia for allowing the petitioner to take new connection from JBVNL at supply voltage of 33 KV having 1000 KVA contract demand. 11.07.2023
1635 Case No.30 of 2020
Tata Steel Limited (TSL)
 Vrs.
 Damodar Valley Corporation (DVC)
Order on Case No. 30 of 2020 04.07.2023
1634 Case No. 16 of 2022
M/s Rungta Mines Ltd. Vrs. Jharkhand Urja Vikas Nigam Limited (JUVNL)
Petition filed under section 86 of the Electricity Act 2003 read alongwith Clause 10.6, 39.1 and 41.1 of the JSERC (Terms and Conditions for Intra State Open Access), Regulations 2016 seeking necessary directioin by upon the Distribution licensee namely, JBVNL to take necessary steps to consider the case of the petitoner for grant of no objection in connection with sale of power/energy in an open market regulated by CERC and administered by NOAR 27.06.2023
1633 Case No. 01 of 2022
SAIL Bokaro Plant Vrs. JREDA
Petition purported to be filed under Regulations 13 read with 15.2 of the JSERC (Renewable Purchase Obligation and its compliance) Regulations, 2016 for exemption from RPO compliance for the period 2016-17, 2017-18, 2018-19, 2019-20, 2020-21 and further periods in terms of 2016 and 2021 (First amendment) Regulations. 27.06.2023
1632 Case No.  05 of 2023
Damodar Valley Corporation (DVC)
Review of order dated 30.01.2023 passed in Case (T) no 01 of 2021 regarding determinatin of ARR for the MYT period from FY 2021-22 to 2025-26 and Tariff for FY 2021-22 27.06.2023
1631 Case No. 04 of 2023
Damodar Valley Corporation (DVC)
Review of order dated 30.01.2023 passed in Case (T) no. 11 of 2020 regarding True-up for FY 2019-20. 27.06.2023
1630 09 of 2023
Jharkhand Bijli Vitran Nigam Limited (JBVNL) Vrs. Solar Energy Corporation of India Limited (SECI), New Delhi
For approval of provisional Power Purchase Agreement (PPA) between Jharkhand Bijli Vitran Nigam Limited and Solar Energy Corporation of India Limited (SECI) for purchase of 100 MW floating solar power to be installed at Getalsud Dam by Solar Energy Corporation of India Limited (SECI) 23.06.2023
1629 08 of 2023
Damodar Valley Corporation
Petition purported to be filed under section 62,64 & 86 of the Electricity Act, 2003 read with the applicable provisions of the DVC Act 1948, interalia for approval towards investment for creations of necessary infrastruture to provide supply of electricity to 11 KV Consumer in the state of Jharkhand by Damodar Valley Cororation in accordance with Regulation 6.12 of JSERC (Terms and Conditions for Determination of Distribution Tariff) Regulations 2020 as amended 23.06.2023
1628 07 of 2023
M/s Sigma HTS LLP
Vrs.
Tata Steel Utilities and Infrastructure Services Ltd
Petition purported to be filed under section 62 (5) and (6) read with section 129 of the Electricity Act, 2003 inter-alia for issuance of a direction to TSUISL to grant appropriate voltage rebate in terms of tariff order 2021-22 published on 24.11.2022 effective from 01.12.2022 23.06.2023
1627 Case No. 06 of 2023
Association of DVC HT Consumers of Jharkhand Vrs. Damodar Valley Corporation (DVC)
Submission of Review petition pertaining to revision of voltage rebate and subsequent issue of corrigendum against the Tariff order for Distribution Activity of Damodar Valley Corporation (DVC) in Jharkhand State- True up for FY 2018-19, APR for FY 2019-20 and ARR & Tariff for FY 2020-21 dated 30.09.2020 issued by Hon'ble JSERC 23.06.2023
1626 Case No. 03 of 2023
Inland Power Limited
Petition for seeking amendment of the JSERC (Terms & Condition for determination of Generation Tariff) Regulation, 2020 under section 61 of the Electricity Act 2003 23.06.2023
1625 Case No. 02 of 2023
Damodar Valley Corporation
Versus
 Association of DVC HT Consumers of Jharkhand
Damodar Valley Corporation (DVC) has submitted an affidavited petition purported to be filled under section 61 and 62 of the Electricity Act, 2003 read with Regulations 22.1 of JSERC (Terms and Conditions for Determination of Distribution Tariff) Regulations 2020 for amendment of clause 10.7 of JSERC (Terms and conditions for Determination of distribution Tariff) Regulations 2020 by which celling/capping of 10% variable component has been made for the recovery of FPPPA for the part of the Damodar Valley area falling within the territory of the state of Jharkhand. 23.06.2023
1624 Case No. 23 of 2020
& MP No. 01 of 2022
Review petition on the order dated 01.10.2020 in Case (T) No. 13 of 2019 on the petition for true up for FY 2018-19, APR for FY 2019-20 and ARR Tariff for FY 2020-21 23.06.2023
1623 19 of 2022
M/s Auto Profiles Ltd. Versus Jharkhand Bijli Vitran Nigam Ltd. &Ors.
Non-compliance of the judgement dated 19.02.2022 passed by the Consumer Grievance Redressal Forum, Chaibasa 23.06.2023
1622 Case No. 17 of 2022
Inland Power Limited (IPL) Vrs. Jharkhand Urja Vikas Nigam Limited & Ors.
Review of order dated 04th November 2022 for True up for FY 2019-20 23.06.2023
1621 Case No.09 of 2019
M/s Vananchal Steel Alloys (Pvt.) Ltd.
Versus
Damodar Valley Corporation (DVC) & Anr
Order on Case No. 09 of 2019 23.06.2023
1620 Case No. 04 of 2020
M/s Gautam Ferro Alloys Vrs. Jharkhand Bijli Vitran Nigam Ltd. & Ors.
Order on Case No. 04 of 2020 23.06.2023
1619 14 of 2023
Inland Power Limited Vrs. Jharkhand Bijli Vitran Nigam Limited
Approval of 3rd Supplementary Power Purchase Agreement (PPA) under Shakti Scheme B-II Round-V or 4300 MT of Coal to be signed between Inland Power Limited (IPL) & Jharkhand Bijli Vitrn Nigam Limited (JBVNL) 19.06.2023
1618 14 of 2023
Inland Power Limited Vrs. Jharkhand Bijli Vitran Nigam Limited
Approval of 3rd Supplementary Power Purchase Agreement (PPA) under Shakti Scheme B-II Round-V or 4300 MT of Coal to be signed between Inland Power Limited (IPL) & Jharkhand Bijli Vitrn Nigam Limited (JBVNL) 12.06.2023
1617 13 of 2023
 Tenughat Vidyut Nigam Limited (TVNL)
Petition purported to be filed under JSERC (Terms and Conditions for Determination of Generation Tariff) Regulations 2020 inter-alia in the clauses of Return on Equity as well as for alignment of depreciation rates as prescribed by Honble Central Electricity Regulatory Commision (CERC) 12.06.2023
1616 12 of 2023
Tata Power Company Limited (TPCL)
Petition purported to be filed under clause 32 & 33 of the JSERC (Terms and Conditions for Determination of Generation Tariff) Regulations 2020 read with clause 45 of the JSERC (Conduct of Business ) Regulations 2016 as well as Section 79(1) (b) of the Electricity Act 2003 seeking removal of difficulties/modification/amendment/review of provisions of JSERC (Terms and Conditions for Determination of Generation Tariff) Regulations, 2020. 12.06.2023
1615 11 of 2023
 Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Petition purported to be filed under JSERC (Rooftop Solar PV Grid Interactive Systems and Net/Gross Metering) Regulations, 2015 inter-alia for amendment of maximum peak capaciity of the grid connected rooftop solar PV system to be installed by any eligible consumer or third party owner. 12.06.2023
1614 Case No. 10 of 2023
 M/s Dilip Buildcon Limited Vrs. Jharkhand Bijli Vitran Nigam Limited
Petition purported under clause 4.7 of the (Electricity Supply Code), Regulations, 2015 inter-alia for allowing the petitioner to take new connection from JBVNL at supply voltage of 33 KV having 1000 KVA contract demand. 12.06.2023
1613 Case No. 17 of 2022
Inland Power Limited (IPL) Vrs. Jharkhand Urja Vikas Nigam Limited & Ors.
Review of order dated 04th November 2022 for True up for FY 2019-20 12.06.2023
1612 Case No. 30 of 2020
Tata Steel Limited
Versus
Damodar Valley Corporation (DVC)
Order on Case No. 30 of 2020 12.06.2023
1611 09 of 2023
Jharkhand Bijli Vitran Nigam Limited (JBVNL) Vrs. Solar Energy Corporation of India Limited (SECI), New Delhi
For approval of provisional Power Purchase Agreement (PPA) between Jharkhand Bijli Vitran Nigam Limited and Solar Energy Corporation of India Limited (SECI) for purchase of 100 MW floating solar power to be installed at Getalsud Dam by Solar Energy Corporation of India Limited (SECI) 16.05.2023
1610 08 of 2023
Damodar Valley Corporation
Petition purported to be filed under section 62,64 & 86 of the Electricity Act, 2003 read with the applicable provisions of the DVC Act 1948, interalia for approval towards investment for creations of necessary infrastruture to provide supply of electricity to 11 KV Consumer in the state of Jharkhand by Damodar Valley Cororation in accordance with Regulation 6.12 of JSERC (Terms and Conditions for Determination of Distribution Tariff) Regulations 2020 as amended 16.05.2023
1609 07 of 2023
M/s Sigma HTS LLP
Vrs.
Tata Steel Utilities and Infrastructure Services Ltd
Petition purported to be filed under section 62 (5) and (6) read with section 129 of the Electricity Act, 2003 inter-alia for issuance of a direction to TSUISL to grant appropriate voltage rebate in terms of tariff order 2021-22 published on 24.11.2022 effective from 01.12.2022 16.05.2023
1608 Case No. 06 of 2023
Association of DVC HT Consumers of Jharkhand Vrs. Damodar Valley Corporation (DVC)
Submission of Review petition pertaining to revision of voltage rebate and subsequent issue of corrigendum against the Tariff order for Distribution Activity of Damodar Valley Corporation (DVC) in Jharkhand State- True up for FY 2018-19, APR for FY 2019-20 and ARR & Tariff for FY 2020-21 dated 30.09.2020 issued by Hon'ble JSERC 16.05.2023
1607 Case No. 30 of 2020
Tata Steel Limited
Versus
Damodar Valley Corporation (DVC)
Order on Case No. 30 of 2020 16.05.2023
1606 Case No. 27 of 2020
Association of DVC HT Consumers of Jharkhand
Versus
Damodar Valley Corporation (DVC)
Submission of Review Petition pertaining to revision of Voltage Rebate and subsequent issue of corrigendum against the Tariff Order for Distribution Activity of Damodar Valley Corporation (DVC) in Jharkhand State - True up for FY 2018-19, APR for FY 2019-20 and ARR & Tariff for FY 2020-21 dated 30.09.2020 issued by Hon'ble JSERC 16.05.2023
1605 Case No. 02 of 2023
Damodar Valley Corporation
Versus
 Association of DVC HT Consumers of Jharkhand
Damodar Valley Corporation (DVC) has submitted an affidavited petition purported to be filled under section 61 and 62 of the Electricity Act, 2003 read with Regulations 22.1 of JSERC (Terms and Conditions for Determination of Distribution Tariff) Regulations 2020 for amendment of clause 10.7 of JSERC (Terms and conditions for Determination of distribution Tariff) Regulations 2020 by which celling/capping of 10% variable component has been made for the recovery of FPPPA for the part of the Damodar Valley area falling within the territory of the state of Jharkhand. 16.05.2023
1604 Case No. 23 of 2020
& MP No. 01 of 2022
Review petition on the order dated 01.10.2020 in Case (T) No. 13 of 2019 on the petition for true up for FY 2018-19, APR for FY 2019-20 and ARR Tariff for FY 2020-21 16.05.2023
1603 19 of 2022
M/s Auto Profiles Ltd. Versus Jharkhand Bijli Vitran Nigam Ltd. &Ors.
Non-compliance of the judgement dated 19.02.2022 passed by the Consumer Grievance Redressal Forum, Chaibasa 16.05.2023
1602 Case No.09 of 2019
M/s Vananchal Steel Alloys (Pvt.) Ltd.
Versus
Damodar Valley Corporation (DVC) & Anr
Order on Case No. 09 of 2019 16.05.2023
1601 Case No. 04 of 2020
M/s Gautam Ferro Alloys Vrs. Jharkhand Bijli Vitran Nigam Ltd. & Ors.
Order on Case No. 04 of 2020 16.05.2023
1600 Case No. 03 of 2023
Inland Power Limited
Petition for seeking amendment of the JSERC (Terms & Condition for determination of Generation Tariff) Regulation, 2020 under section 61 of the Electricity Act 2003 16.05.2023
1599 Case No. 03 of 2023
Inland Power Limited
Petition for seeking amendment of the JSERC (Terms & Condition for determination of Generation Tariff) Regulation, 2020 under section 61 of the Electricity Act 2003 12.05.2023
1598 Case No. 18 of 2022
Tata Power Company Limited (TPCL) Vrs. Tata Steel Limited (TSL)
Review of order dated 04 November 2022 for True-up 2019-20, APR-2020-21, Business Plan & MYT for control period 2021-22 to 2025-26 12.05.2023
1597 Case No. 17 of 2022
Inland Power Limited (IPL) Vrs. Jharkhand Urja Vikas Nigam Limited & Ors.
Review of order dated 04th November 2022 for True up for FY 2019-20 12.05.2023
1596 Case No. 16 of 2022
M/s Rungta Mines Ltd. Vrs. Jharkhand Urja Vikas Nigam Limited (JUVNL)
Petition filed under section 86 of the Electricity Act 2003 read alongwith Clause 10.6, 39.1 and 41.1 of the JSERC (Terms and Conditions for Intra State Open Access), Regulations 2016 seeking necessary directioin by upon the Distribution licensee namely, JBVNL to take necessary steps to consider the case of the petitoner for grant of no objection in connection with sale of power/energy in an open market regulated by CERC and administered by NOAR 12.05.2023
1595 Case No. 01 of 2022
SAIL Bokaro Plant Vrs. JREDA
Petition purported to be filed under Regulations 13 read with 15.2 of the JSERC (Renewable Purchase Obligation and its compliance) Regulations, 2016 for exemption from RPO compliance for the period 2016-17, 2017-18, 2018-19, 2019-20, 2020-21 and further periods in terms of 2016 and 2021 (First amendment) Regulations. 12.05.2023
1594 Case No. 01 of 2021
Indian Railways
Vrs.
Jharkhand Urja Sancharan Nigam Ltd.
Order on Case No. 01 of 2021 12.05.2023
1593 Case No.  05 of 2023
Damodar Valley Corporation (DVC)
Review of order dated 30.01.2023 passed in Case (T) no 01 of 2021 regarding determinatin of ARR for the MYT period from FY 2021-22 to 2025-26 and Tariff for FY 2021-22 12.05.2023
1592 Case No. 04 of 2023
Damodar Valley Corporation (DVC)
Review of order dated 30.01.2023 passed in Case (T) no. 11 of 2020 regarding True-up for FY 2019-20. 12.05.2023
1591 Case No. 18 of 2022
Tata Power Company Limited (TPCL) Vrs. Tata Steel Limited (TSL)
Review of order dated 04 November 2022 for True-up 2019-20, APR-2020-21, Business Plan & MYT for control period 2021-22 to 2025-26 31.03.2023
1590 Case No. 16 of 2022
M/s Rungta Mines Ltd. Vrs. Jharkhand Urja Vikas Nigam Limited (JUVNL)
Petition filed under section 86 of the Electricity Act 2003 read alongwith Clause 10.6, 39.1 and 41.1 of the JSERC (Terms and Conditions for Intra State Open Access), Regulations 2016 seeking necessary directioin by upon the Distribution licensee namely, JBVNL to take necessary steps to consider the case of the petitoner for grant of no objection in connection with sale of power/energy in an open market regulated by CERC and administered by NOAR 31.03.2023
1589 Case No. 01 of 2022
SAIL Bokaro Plant Vrs. JREDA
Petition purported to be filed under Regulations 13 read with 15.2 of the JSERC (Renewable Purchase Obligation and its compliance) Regulations, 2016 for exemption from RPO compliance for the period 2016-17, 2017-18, 2018-19, 2019-20, 2020-21 and further periods in terms of 2016 and 2021 (First amendment) Regulations. 31.03.2023
1588 Case No. 01 of 2021
Indian Railways
Vrs.
Jharkhand Urja Sancharan Nigam Ltd.
Order on Case No. 01 of 2021 31.03.2023
1587 Case No.26 of 2020
M/s Grasim Industries Limited
Vrs.
 Jharkhand Bijli Vitran Nigam Limited
Petition filed under clause 8.12 and 8.13 of JSERC (Utilization of surplus Capacity of CPP based on Conventional Fuel) Regulation 2010 31.03.2023
1586 Case No. 03 of 2023
Inland Power Limited
Petition for seeking amendment of the JSERC (Terms & Condition for determination of Generation Tariff) Regulation, 2020 under section 61 of the Electricity Act 2003 31.03.2023
1585 Case No. 19 of 2022
M/s Auto Profiles Ltd.
Versus
Jharkhand Bijli Vitran Nigam Ltd. &Ors.
Non-compliance of the judgement dated 19.02.2022 passed by the Consumer Grievance Redressal Forum, Chaibasa 28.03.2023
1584 Case No. 30 of 2020
 Tata Steel Limited
Versus
Damodar Valley Corporation (DVC)
Order on Case No. 30 of 2020 28.03.2023
1583 Case No. 27 of 2020
Association of DVC HT Consumers of Jharkhand
Versus
Damodar Valley Corporation (DVC)
Submission of Review Petition pertaining to revision of Voltage Rebate and subsequent issue of corrigendum against the Tariff Order for Distribution Activity of Damodar Valley Corporation (DVC) in Jharkhand State - True up for FY 2018-19, APR for FY 2019-20 and ARR & Tariff for FY 2020-21 dated 30.09.2020 issued by Hon'ble JSERC 28.03.2023
1582 Case No. 23 of 2020 & MP No. 01 of 2022
Jharkhand Bijli Vitran Nigam Limited Versus
Jharkhand Small Industries Association (JSIA)
Review petition on the order dated 01.10.2020 in Case (T) No. 13 of 2019 on the petition for true up for FY 2018-19, APR for FY 2019-20 and ARR Tariff for FY 2020-21 28.03.2023
1581 Case No. 04 of 2020
M/s Gautam Ferro Alloys Vrs. Jharkhand Bijli Vitran Nigam Ltd. & Ors.
Order on Case No. 04 of 2020 28.03.2023
1580 Case No.09 of 2019
M/s Vananchal Steel Alloys (Pvt.) Ltd.
Versus
Damodar Valley Corporation (DVC) & Anr
Order on Case No. 09 of 2019 28.03.2023
1579 Case No. 02 of 2023
Damodar Valley Corporation
Versus
 Association of DVC HT Consumers of Jharkhand
Damodar Valley Corporation (DVC) has submitted an affidavited petition purported to be filled under section 61 and 62 of the Electricity Act, 2003 read with Regulations 22.1 of JSERC (Terms and Conditions for Determination of Distribution Tariff) Regulations 2020 for amendment of clause 10.7 of JSERC (Terms and conditions for Determination of distribution Tariff) Regulations 2020 by which celling/capping of 10% variable component has been made for the recovery of FPPPA for the part of the Damodar Valley area falling within the territory of the state of Jharkhand. 28.03.2023
1578 Case No.01 of 2023
Tata Steel Utitlites and Infrastructure Services Ltd.
For approval of capital expenditure 28.03.2023
1577 Case No. 10 of 2022
M/s Usha Martin Limited Vrs. JUVNL & Ors
Order on Case No 10 of 2022 13.03.2023
1576 Case No. 10 of 2022
M/s Usha Martin Limited Vrs. JUVNL & Ors
Order on Case No 10 of 2022 03.03.2023
1575 Case No.26 of 2020
M/s Grasim Industries Limited
Vrs.
 Jharkhand Bijli Vitran Nigam Limited
Petition filed under clause 8.12 and 8.13 of JSERC (Utilization of surplus Capacity of CPP based on Conventional Fuel) Regulation 2010 03.03.2023
1574 Miscellaneous Petition No. 03 of 2022
Damodar Valley Corporation (DVC)
Determination of single part tariff applicable for public EV Charging Stations operating in the supply area of DVC in the State of Jharkhand 28.02.2023
1573 Case No.26 of 2020
M/s Grasim Industries Limited
Vrs.
 Jharkhand Bijli Vitran Nigam Limited
Petition filed under clause 8.12 and 8.13 of JSERC (Utilization of surplus Capacity of CPP based on Conventional Fuel) Regulation 2010 28.02.2023
1572 Case No.09 of 2019
M/s Vananchal Steel Alloys (Pvt.) Ltd.
Versus
Damodar Valley Corporation (DVC) & Anr
Order on Case No. 09 of 2019 28.02.2023
1571 04 of 2020
M/s Gautam Ferro Alloys
Vrs.
 Jharkhand Bijli Vitran Nigam Ltd. & Others
Order on Case No. 04 of 2020 28.02.2023
1570 Case No. 10 of 2022
M/s Usha Martin Limited Vrs. JUVNL & Ors
Order on Case No 10 of 2022 28.02.2023
1569 Case No. 01 of 2021
Indian Railways
Vrs.
Jharkhand Urja Sancharan Nigam Ltd.
Order on Case No. 01 of 2021 28.02.2023
1568 Case No. 18 of 2022
Tata Power Company Limited (TPCL) Vrs. Tata Steel Limited (TSL)
Review of order dated 04 November 2022 for True-up 2019-20, APR-2020-21, Business Plan & MYT for control period 2021-22 to 2025-26 24.022023
1567 Case No. 17 of 2022
Inland Power Limited (IPL) Vrs. Jharkhand Urja Vikas Nigam Limited & Ors.
Review of order dated 04th November 2022 for True up for FY 2019-20 24.02.2023
1566 Miscellaneous Petition No. 03 of 2022
Damodar Valley Corporation (DVC)
Determination of single part tariff applicable for public EV Charging Stations operating in the supply area of DVC in the State of Jharkhand 24.02.2023
1565 Case No. 16 of 2022
M/s Rungta Mines Ltd. Vrs. Jharkhand Urja Vikas Nigam Limited (JUVNL)
Petition filed under section 86 of the Electricity Act 2003 read alongwith Clause 10.6, 39.1 and 41.1 of the JSERC (Terms and Conditions for Intra State Open Access), Regulations 2016 seeking necessary directioin by upon the Distribution licensee namely, JBVNL to take necessary steps to consider the case of the petitoner for grant of no objection in connection with sale of power/energy in an open market regulated by CERC and administered by NOAR 24.02.2023
1564 Case No. 01 of 2022
SAIL Bokaro Plant Vrs. JREDA
Petition purported to be filed under Regulations 13 read with 15.2 of the JSERC (Renewable Purchase Obligation and its compliance) Regulations, 2016 for exemption from RPO compliance for the period 2016-17, 2017-18, 2018-19, 2019-20, 2020-21 and further periods in terms of 2016 and 2021 (First amendment) Regulations. 24.02.2023
1563 Case No. 30 of 2020
Tata Steel Limited
Versus
Damodar Valley Corporation (DVC)
Order on Case No. 30 of 2020 24.02.2023
1562 Case No. 29 of 2020
SAIL-Bokaro Steel Plant
Vrs.
 Damodar Valley Corporation
Order on Case No. 29 of 2020 24.02.2023
1561 Case No. 27 of 2020
Association of DVC HT Consumers of Jharkhand Versus Damodar Valley Corporation (DVC)
Submission of Review Petition pertaining to revision of Voltage Rebate and subsequent issue of corrigendum against the Tariff Order for Distribution Activity of Damodar Valley Corporation (DVC) in Jharkhand State - True up for FY 2018-19, APR for FY 2019-20 and ARR & Tariff for FY 2020-21 dated 30.09.2020 issued by Hon'ble JSERC 24.02.2023
1560 Case No.22 of 2020
Association of DVC HT Consumers of Jharkhand
Vrs.
Damodar Valley Corporation (DVC)
Determination of Retail Tariff and implementaion of refund to the consumers of DVC in the area of Jharkhand for the period from 01.4.2006 to 31.10.2012 24.02.2023
1579 08 of 2022
 M/s Vijayshree Autocom Ltd. Vrs. Jharkhand Bili Vitran Nigam Ltd.
Petition filed under Regulation 26 of the JSERC (Guidelines for Establishment of Forum for Redressal of Grievance of the Consumers and Electricity Ombudsman) Regulations, 2021 read with Section 142,146,149 of the Electricity Act 2003, against the Licensee JBVNL for non-compliance of the order passed by Ld.VUSNF at Karandih, Jamshedpur. 21.02.2023
1578 Case No.26 of 2020
M/s Grasim Industries Limited
Vrs.
 Jharkhand Bijli Vitran Nigam Limited
Petition filed under clause 8.12 and 8.13 of JSERC (Utilization of surplus Capacity of CPP based on Conventional Fuel) Regulation 2010 21.02.2023
1577 Case No.09 of 2019
M/s Vananchal Steel Alloys (Pvt.) Ltd.
Versus
Damodar Valley Corporation (DVC) & Anr
Order on Case No. 09 of 2019 21.02.2023
1576 Case No.23 of 2020
Jharkhand Bijli Vitran Nigam Limited
Review petition on the order dated 01.10.2020 in Case (T) No. 13 of 2019 on the petition for true up for FY 2018-19, APR for FY 2019-20 and ARR Tariff for FY 2020-21 21.02.2023
1575 04 of 2020
M/s Gautam Ferro Alloys
Vrs.
 Jharkhand Bijli Vitran Nigam Ltd. & Others
Order on Case No. 04 of 2020 21.02.2023
1574 19 of 2022
M/s Auto Profiles Ltd. Versus Jharkhand Bijli Vitran Nigam Ltd. &Ors.
Non-compliance of the judgement dated 19.02.2022 passed by the Consumer Grievance Redressal Forum, Chaibasa 21.02.2023
1573 Case No. 10 of 2022
M/s Usha Martin Limited Vrs. JUVNL & Ors
Order on Case No 10 of 2022 20.02.2023
1572 Case No. 10 of 2022
M/s Usha Martin Limited Vrs. JUVNL & Ors
Order on Case No 10 of 2022 14.02.2023
1571 Case No. 01 of 2021
Indian Railways
Vrs.
Jharkhand Urja Sancharan Nigam Ltd.
Order on Case No. 01 of 2021 14.02.2023
1570 Case No.26 of 2020
M/s Grasim Industries Limited
Vrs.
 Jharkhand Bijli Vitran Nigam Limited
Petition filed under clause 8.12 and 8.13 of JSERC (Utilization of surplus Capacity of CPP based on Conventional Fuel) Regulation 2010 14.02.2023
1569 Case No.09 of 2019
M/s Vananchal Steel Alloys (Pvt.) Ltd.
Versus
Damodar Valley Corporation (DVC) & Anr
Order on Case No. 09 of 2019 14.02.2023
1568 Case No. 04 of 2020
M/s Gautam Ferro Alloys Vrs. Jharkhand Bijli Vitran Nigam Ltd. & Ors.
Order on Case No. 04 of 2020 24.01.2023
1567 Case No.26 of 2020
M/s Grasim Industries Limited
Vrs.
 Jharkhand Bijli Vitran Nigam Limited
Petition filed under clause 8.12 and 8.13 of JSERC (Utilization of surplus Capacity of CPP based on Conventional Fuel) Regulation 2010 24.01.2023
1566 Case No. 23 of 2020
& MP No. 01 of 2022
Review petition on the order dated 01.10.2020 in Case (T) No. 13 of 2019 on the petition for true up for FY 2018-19, APR for FY 2019-20 and ARR Tariff for FY 2020-21 24.01.2023
1565 Case No.09 of 2019
M/s Vananchal Steel Alloys (Pvt.) Ltd.
Versus
Damodar Valley Corporation (DVC) & Anr
Order on Case No. 09 of 2019 24.01.2023
1564 Case No. 18 of 2022
Tata Power Company Limited (TPCL) Vrs. Tata Steel Limited (TSL)
Review of order dated 04 November 2022 for True-up 2019-20, APR-2020-21, Business Plan & MYT for control period 2021-22 to 2025-26 20.01.2023
1563 Case No. 17 of 2022
Inland Power Limited (IPL) Vrs. Jharkhand Urja Vikas Nigam Limited & Ors.
Review of order dated 04th November 2022 for True up for FY 2019-20 20.01.2023
1562 Miscellaneous Petition No. 03 of 2022
Damodar Valley Corporation (DVC)
Determination of single part tariff applicable for public EV Charging Stations operating in the supply area of DVC in the State of Jharkhand 20.01.2023
1561 Miscellaneous Petition No. 02 of 2022
Inland Power Limited (IPL)
Versus
 1. Jharkhand Urja Vikas Nigam Limited 2. Jharhand Bijli Vitran Nigam Limited.
Pursuance of order dated 16.09.2022 passed by Hon'ble APTEL in Appeal No.411 of 2019 for revised determination of fixed charges for FY 2014-15. 20.01.2023
1560 Case No. 16 of 2022
M/s Rungta Mines Ltd. Vrs. Jharkhand Urja Vikas Nigam Limited (JUVNL)
Petition filed under section 86 of the Electricity Act 2003 read alongwith Clause 10.6, 39.1 and 41.1 of the JSERC (Terms and Conditions for Intra State Open Access), Regulations 2016 seeking necessary directioin by upon the Distribution licensee namely, JBVNL to take necessary steps to consider the case of the petitoner for grant of no objection in connection with sale of power/energy in an open market regulated by CERC and administered by NOAR 20.01.2023
1559 Case No. 06 of 2022
Damodar Valley Corporation (DVC)
Affidavated petition purported to be filed under Regulations 6.29 of the JSERC (Terms and Conditions for Determination of Distribution Tariff) Regulations, 2020 and its amendments thereof for approval of Power Usage Agreement (PUA) between Damodar Valley Corporation (DVC) and NTPC Renewable Energy Ltd (NTPC REL) for purchase of 100 MW Solar Power by DVC under CPSU Scheme. 20.01.2023
1558 Case No. 05 of 2022
Damodar Valley Corporation (DVC)
Affidavated petition purported to be filed under Regulations 6.29 of the JSERC (Terms and Conditions for Determination of Distribution Tariff) Regulations, 2020 and its amendments thereof for approval of Power Sale Agreement (PSA) between Damodar Valley Corporation (DVC) and Solar Energy Corporation India Limited (SECI) for purchase of 200 MW Assured Peak Power by DVC, which in turn to be procured by SECI from ISTS-Connected RE Projects with storage to be Developed by Renewable Power Developers (RPD). 20.01.2023
1557 Case No. 03 of 2022
Damodar Valley Corporation (DVC)
Petition purported to be filed under Regulations 6.29 of the JSERC (Terms and Conditions for Determination of Distribution Tariff) Regulations, 2020 and its amendments thereof for approval of Power Purchase Agreement (PPA) between Damodar Valley Corporation (DVC) and Jyotikiran Energy Mumbai Pvt. Ltd. (JEM) for purchase of power by DVC from the solar photovoltaic power plant of 1137 kWp (Project 1 : 493.12kWp, Project 2: 446.9 kWp and Project 3: 196.98 kWp) to be commissioned at Koderma Thermal Power Station (KTPS) of DVC at Koderma district in the State of Jharkhand. 20.01.2023
1556 Case No.02 of 2022
Damodar Valley Corporation (DVC)
Petition purported to be filed under Regulations 6.29 of the JSERC (Terms and Conditions for Determination of Distribution Tariff) Regulations, 2020 and its amendments thereof for approval of Power Purchase Agreement (PPA) between Damodar Valley Corporation (DVC) and Jyotikiran Energy Mumbai Pvt. Ltd. (JEM) for purchase of power by DVC from the solar photovoltaic power plant of 278.72 kWp to be commissioned at Maithon of DVC Maithon, P.O. – Maithon Dam at Dhanbad District in the State of Jharkhand. 20.01.2023
1555 Case No. 01 of 2022
SAIL Bokaro Plant Vrs. JREDA
Petition purported to be filed under Regulations 13 read with 15.2 of the JSERC (Renewable Purchase Obligation and its compliance) Regulations, 2016 for exemption from RPO compliance for the period 2016-17, 2017-18, 2018-19, 2019-20, 2020-21 and further periods in terms of 2016 and 2021 (First amendment) Regulations. 20.01.2023
1554 Case No. 30 of 2020
Tata Steel Limited
Versus
Damodar Valley Corporation (DVC)
Order on Case No. 30 of 2020 20.01.2023
1553 Case No. 29 of 2020
SAIL-Bokaro Steel Plant
Vrs.
 Damodar Valley Corporation
Order on Case No. 29 of 2020 20.01.2023
1552 Case No. 27 of 2020
Association of DVC HT Consumers of Jharkhand Versus Damodar Valley Corporation (DVC)
Submission of Review Petition pertaining to revision of Voltage Rebate and subsequent issue of corrigendum against the Tariff Order for Distribution Activity of Damodar Valley Corporation (DVC) in Jharkhand State - True up for FY 2018-19, APR for FY 2019-20 and ARR & Tariff for FY 2020-21 dated 30.09.2020 issued by Hon'ble JSERC 20.01.2023
1551 Case No.22 of 2020
Association of DVC HT Consumers of Jharkhand
Vrs.
Damodar Valley Corporation (DVC)
Determination of Retail Tariff and implementaion of refund to the consumers of DVC in the area of Jharkhand for the period from 01.4.2006 to 31.10.2012 20.01.2023
1550 04 of 2020
M/s Gautam Ferro Alloys
Vrs.
 Jharkhand Bijli Vitran Nigam Ltd. & Others
Order on Case No. 04 of 2020 20.01.2023
1549 19 of 2022
M/s Auto Profiles Ltd. Versus Jharkhand Bijli Vitran Nigam Ltd. &Ors.
Non-compliance of the judgement dated 19.02.2022 passed by the Consumer Grievance Redressal Forum, Chaibasa 17.01.2023
1548 04 of 2020
M/s Gautam Ferro Alloys
Vrs.
 Jharkhand Bijli Vitran Nigam Ltd. & Others
Order on Case No. 04 of 2020 17.01.2023
1547 08 of 2022
 M/s Vijayshree Autocom Ltd. Vrs. Jharkhand Bili Vitran Nigam Ltd.
Petition filed under Regulation 26 of the JSERC (Guidelines for Establishment of Forum for Redressal of Grievance of the Consumers and Electricity Ombudsman) Regulations, 2021 read with Section 142,146,149 of the Electricity Act 2003, against the Licensee JBVNL for non-compliance of the order passed by Ld.VUSNF at Karandih, Jamshedpur. 16.01.2023
1546 Case No. 10 of 2022
M/s Usha Martin Limited Vrs. JUVNL & Ors
Order on Case No 10 of 2022 16.01.2023
1545 Case No. 29 of 2020
SAIL-Bokaro Steel Plant
Vrs.
 Damodar Valley Corporation
Order on Case No. 29 of 2020 16.01.2023
1544 Case No. 27 of 2020
Association of DVC HT Consumers of Jharkhand Versus Damodar Valley Corporation (DVC)
Submission of Review Petition pertaining to revision of Voltage Rebate and subsequent issue of corrigendum against the Tariff Order for Distribution Activity of Damodar Valley Corporation (DVC) in Jharkhand State - True up for FY 2018-19, APR for FY 2019-20 and ARR & Tariff for FY 2020-21 dated 30.09.2020 issued by Hon'ble JSERC 16.01.2023
1543 Case No.26 of 2020
M/s Grasim Industries Limited
Vrs.
 Jharkhand Bijli Vitran Nigam Limited
Petition filed under clause 8.12 and 8.13 of JSERC (Utilization of surplus Capacity of CPP based on Conventional Fuel) Regulation 2010 10.01.2023
1542 Case No.23 of 2020
Jharkhand Bijli Vitran Nigam Limited
Review petition on the order dated 01.10.2020 in Case (T) No. 13 of 2019 on the petition for true up for FY 2018-19, APR for FY 2019-20 and ARR Tariff for FY 2020-21 10.01.2023
1541 Case No. 09 of 2019
M/s Vananchal Steel Alloys Private Limited Versus Damodar Valley Corporation & another
Order on Case No. 09 of 2019 10.01.2023
1540 Case No. 01 of 2021
Indian Railways
Vrs.
Jharkhand Urja Sancharan Nigam Ltd.
Order on Case No. 01 of 2021 10.01.2023
1539 08 of 2022
 M/s Vijayshree Autocom Ltd. Vrs. Jharkhand Bili Vitran Nigam Ltd.
Petition filed under Regulation 26 of the JSERC (Guidelines for Establishment of Forum for Redressal of Grievance of the Consumers and Electricity Ombudsman) Regulations, 2021 read with Section 142,146,149 of the Electricity Act 2003, against the Licensee JBVNL for non-compliance of the order passed by Ld.VUSNF at Karandih, Jamshedpur. 20.12.2022
1538 Case No. 04 of 2020
M/s Gautam Ferro Alloys Vrs. Jharkhand Bijli Vitran Nigam Ltd. & Ors.
Order on Case No. 04 of 2020 20.12.2022
1537 Miscellaneous Petition No. 02 of 2020
 Jharkhand Bijli Vitran Nigam Limited (JBVNL)
Seeking extension of the timeline provided in Tariff order dated 01st October 2020 of JBVNL for metering of unmtered consumers 20.12.2022
1536 08 of 2022
 M/s Vijayshree Autocom Ltd. Vrs. Jharkhand Bili Vitran Nigam Ltd.
Petition filed under Regulation 26 of the JSERC (Guidelines for Establishment of Forum for Redressal of Grievance of the Consumers and Electricity Ombudsman) Regulations, 2021 read with Section 142,146,149 of the Electricity Act 2003, against the Licensee JBVNL for non-compliance of the order passed by Ld.VUSNF at Karandih, Jamshedpur. 13.12.2022
1535 Case No. 29 of 2020
SAIL-Bokaro Steel Plant
Vrs.
 Damodar Valley Corporation
Order on Case No. 29 of 2020 13.12.2022
1534 Case No. 27 of 2020
Association of DVC HT Consumers of Jharkhand Versus Damodar Valley Corporation (DVC)
Submission of Review Petition pertaining to revision of Voltage Rebate and subsequent issue of corrigendum against the Tariff Order for Distribution Activity of Damodar Valley Corporation (DVC) in Jharkhand State - True up for FY 2018-19, APR for FY 2019-20 and ARR & Tariff for FY 2020-21 dated 30.09.2020 issued by Hon'ble JSERC 13.12.2022
1533 Case No.22 of 2020
Association of DVC HT Consumers of Jharkhand
Vrs.
Damodar Valley Corporation (DVC)
Determination of Retail Tariff and implementaion of refund to the consumers of DVC in the area of Jharkhand for the period from 01.4.2006 to 31.10.2012 13.12.2022
1532 Case No.26 of 2020
M/s Grasim Industries Limited
Vrs.
 Jharkhand Bijli Vitran Nigam Limited
Petition filed under clause 8.12 and 8.13 of JSERC (Utilization of surplus Capacity of CPP based on Conventional Fuel) Regulation 2010 09.12.2022
1531 Case No.23 of 2020
Jharkhand Bijli Vitran Nigam Limited
Review petition on the order dated 01.10.2020 in Case (T) No. 13 of 2019 on the petition for true up for FY 2018-19, APR for FY 2019-20 and ARR Tariff for FY 2020-21 09.12.2022
1530 Case No. 04 of 2020
M/s Gautam Ferro Alloys Vrs. Jharkhand Bijli Vitran Nigam Ltd. & Ors.
Order on Case No. 04 of 2020 09.12.2022
1529 Case No. 09 of 2019
M/s Vananchal Steel Alloys Private Limited Versus Damodar Valley Corporation & another
Order on Case No. 09 of 2019 09.12.2022
1528 Case No. 12 of 2022 Order on Case No 12 of 2022 02.12.2022
1527 Case No. 10 of 2022
M/s Usha Martin Limited Vrs. JUVNL & Ors
Order on Case No 10 of 2022 02.12.2022
1526 07 of 2022
 Jharkhand Urja Sancharan Nigam Limited (JUSNL)
Jharkhand Urja Sancharan Nigam Ltd. (JUSNL) Review of order dated 30.12.2020 on true-up 2015-16 & 2016-17 02.12.2022
1525 Case No. 01 of 2021
Indian Railways
Vrs.
Jharkhand Urja Sancharan Nigam Ltd.
Order on Case No. 01 of 2021 02.12.2022
1524 06 of 2022
Damodar Valley Corporation (DVC)
Affidavated petition purported to be filed under Regulations 6.29 of the JSERC (Terms and Conditions for Determination of Distribution Tariff) Regulations, 2020 and its amendments thereof for approval of Power Usage Agreement (PUA) between Damodar Valley Corporation (DVC) and NTPC Renewable Energy Ltd (NTPC REL) for purchase of 100 MW Solar Power by DVC under CPSU Scheme. 22.11.2022
1523 Case No. 05 of 2022
Damodar Valley Corporation (DVC)
Affidavated petition purported to be filed under Regulations 6.29 of the JSERC (Terms and Conditions for Determination of Distribution Tariff) Regulations, 2020 and its amendments thereof for approval of Power Sale Agreement (PSA) between Damodar Valley Corporation (DVC) and Solar Energy Corporation India Limited (SECI) for purchase of 200 MW Assured Peak Power by DVC, which in turn to be procured by SECI from ISTS-Connected RE Projects with storage to be Developed by Renewable Power Developers (RPD). 22.11.2022
1522 Case No. 03 of 2022
Damodar Valley Corporation (DVC)
Petition purported to be filed under Regulations 6.29 of the JSERC (Terms and Conditions for Determination of Distribution Tariff) Regulations, 2020 and its amendments thereof for approval of Power Purchase Agreement (PPA) between Damodar Valley Corporation (DVC) and Jyotikiran Energy Mumbai Pvt. Ltd. (JEM) for purchase of power by DVC from the solar photovoltaic power plant of 1137 kWp (Project 1 : 493.12kWp, Project 2: 446.9 kWp and Project 3: 196.98 kWp) to be commissioned at Koderma Thermal Power Station (KTPS) of DVC at Koderma district in the State of Jharkhand. 22.11.2022
1521 Case No.02 of 2022
Damodar Valley Corporation (DVC)
Petition purported to be filed under Regulations 6.29 of the JSERC (Terms and Conditions for Determination of Distribution Tariff) Regulations, 2020 and its amendments thereof for approval of Power Purchase Agreement (PPA) between Damodar Valley Corporation (DVC) and Jyotikiran Energy Mumbai Pvt. Ltd. (JEM) for purchase of power by DVC from the solar photovoltaic power plant of 278.72 kWp to be commissioned at Maithon of DVC Maithon, P.O. – Maithon Dam at Dhanbad District in the State of Jharkhand. 22.11.2022
1520 Case No. 01 of 2022
SAIL Bokaro Plant Vrs. JREDA
Petition purported to be filed under Regulations 13 read with 15.2 of the JSERC (Renewable Purchase Obligation and its compliance) Regulations, 2016 for exemption from RPO compliance for the period 2016-17, 2017-18, 2018-19, 2019-20, 2020-21 and further periods in terms of 2016 and 2021 (First amendment) Regulations. 22.11.2022
1519 Case No. 01 of 2021
Indian Railways
Vrs.
Jharkhand Urja Sancharan Nigam Ltd.
Order on Case No. 01 of 2021 22.11.2022
1518 Case No. 30 of 2020
Tata Steel Limited
Versus
Damodar Valley Corporation (DVC)
Order on Case No. 30 of 2020 22.11.2022
1517 Case No. 04 of 2020
M/s Gautam Ferro Alloys Vrs. Jharkhand Bijli Vitran Nigam Ltd. & Ors.
Order on Case No. 04 of 2020 22.11.2022
1516 Miscellaneous Petition No. 02 of 2020
Jharkhand Bijli Vitran Nigam Limted
Order on MP No. 02 of 2020 22.11.2022
1515 Case No. 04 of 2022
M/s Adani Power(Jharkhand) Ltd. (APJL) Vrs. Jharkhand Bijli Vitran Nigam Ltd. (JBVNL)
Affidavited petition purported to be filed under clause 4.7 of JSERC (Electricity Supply Code) Regulations, 2015 interalia for allowing the petitioner to avail power supply at 132 KV for load of 2 MVA going up to 40 MW (peak load) and for approval of revised load schedule with fixed time period. 01.11.2022
1514 Case No. 15 of 2022
Tata Steel Utilities and Infrastructure Limited (JSUISL)
Versus
Damodar Valley Corporation (DVC)
Approval of Power Purchase Agreement between Damodar Valley Corporation (DVC) and Tata Steel Utitlites and Infrastructure Services Limited (TSUISL) 01.11.2022
1513 Case No. 12 of 2022
M/s Satyug Foods Pvt. Ltd. Versus Jharkhand Urja Vikas Nigam Limited & Ors
Order on Case No 12 of 2022 01.11.2022
1512 Case No. 10 of 2022
M/s Usha Martin Limited Vrs. JUVNL & Ors
Order on Case No 10 of 2022 01.11.2022
1511 08 of 2022
 M/s Vijayshree Autocom Ltd. Vrs. Jharkhand Bili Vitran Nigam Ltd.
Petition filed under Regulation 26 of the JSERC (Guidelines for Establishment of Forum for Redressal of Grievance of the Consumers and Electricity Ombudsman) Regulations, 2021 read with Section 142,146,149 of the Electricity Act 2003, against the Licensee JBVNL for non-compliance of the order passed by Ld.VUSNF at Karandih, Jamshedpur. 01.11.2022
1510 07 of 2022
 Jharkhand Urja Sancharan Nigam Limited (JUSNL)
Jharkhand Urja Sancharan Nigam Ltd. (JUSNL) Review of order dated 30.12.2020 on true-up 2015-16 & 2016-17 01.11.2022
1509 Case No.26 of 2020
M/s Grasim Industries Limited
Vrs.
 Jharkhand Bijli Vitran Nigam Limited
Petition filed under clause 8.12 and 8.13 of JSERC (Utilization of surplus Capacity of CPP based on Conventional Fuel) Regulation 2010 01.11.2022
1508 Case No. 25 of 2020
Tata Steel Utilities and Infrastructure Services Limited (TSUISL)
For review of tariff order dated 29.09.2020 01.11.2022
1507 Case No.23 of 2020
Jharkhand Bijli Vitran Nigam Limited
Review petition on the order dated 01.10.2020 in Case (T) No. 13 of 2019 on the petition for true up for FY 2018-19, APR for FY 2019-20 and ARR Tariff for FY 2020-21 01.11.2022
1506 Case No. 09 of 2019
M/s Vananchal Steel Alloys Private Limited Versus Damodar Valley Corporation & another
Order on Case No. 09 of 2019 01.11.2022
1505 Case No. 04 of 2022
M/s Adani Power(Jharkhand) Ltd. (APJL) Vrs. Jharkhand Bijli Vitran Nigam Ltd. (JBVNL)
Affidavited petition purported to be filed under clause 4.7 of JSERC (Electricity Supply Code) Regulations, 2015 interalia for allowing the petitioner to avail power supply at 132 KV for load of 2 MVA going up to 40 MW (peak load) and for approval of revised load schedule with fixed time period. 28.10.2022
1504 Case No. 30 of 2020
Tata Steel Limited
Versus
Damodar Valley Corporation (DVC)
Order on Case No. 30 of 2020 28.10.2022
1503 Case No. 29 of 2020
SAIL-Bokaro Steel Plant
Vrs.
 Damodar Valley Corporation
Order on Case No. 29 of 2020 28.10.2022
1502 Case No. 27 of 2020
Association of DVC HT Consumers of Jharkhand Versus Damodar Valley Corporation (DVC)
Submission of Review Petition pertaining to revision of Voltage Rebate and subsequent issue of corrigendum against the Tariff Order for Distribution Activity of Damodar Valley Corporation (DVC) in Jharkhand State - True up for FY 2018-19, APR for FY 2019-20 and ARR & Tariff for FY 2020-21 dated 30.09.2020 issued by Hon'ble JSERC 28.10.2022
1501 Case No.22 of 2020
Association of DVC HT Consumers of Jharkhand
Vrs.
Damodar Valley Corporation (DVC)
Determination of Retail Tariff and implementaion of refund to the consumers of DVC in the area of Jharkhand for the period from 01.4.2006 to 31.10.2012 28.10.2022
1500 08 of 2022
 M/s Vijayshree Autocom Ltd. Vrs. Jharkhand Bili Vitran Nigam Ltd.
Petition filed under Regulation 26 of the JSERC (Guidelines for Establishment of Forum for Redressal of Grievance of the Consumers and Electricity Ombudsman) Regulations, 2021 read with Section 142,146,149 of the Electricity Act 2003, against the Licensee JBVNL for non-compliance of the order passed by Ld.VUSNF at Karandih, Jamshedpur. 18.10.2022
1499 06 of 2022
Damodar Valley Corporation (DVC)
Affidavated petition purported to be filed under Regulations 6.29 of the JSERC (Terms and Conditions for Determination of Distribution Tariff) Regulations, 2020 and its amendments thereof for approval of Power Usage Agreement (PUA) between Damodar Valley Corporation (DVC) and NTPC Renewable Energy Ltd (NTPC REL) for purchase of 100 MW Solar Power by DVC under CPSU Scheme. 18.10.2022
1498 Case No. 05 of 2022
Damodar Valley Corporation (DVC)
Affidavated petition purported to be filed under Regulations 6.29 of the JSERC (Terms and Conditions for Determination of Distribution Tariff) Regulations, 2020 and its amendments thereof for approval of Power Sale Agreement (PSA) between Damodar Valley Corporation (DVC) and Solar Energy Corporation India Limited (SECI) for purchase of 200 MW Assured Peak Power by DVC, which in turn to be procured by SECI from ISTS-Connected RE Projects with storage to be Developed by Renewable Power Developers (RPD). 18.10.2022
1497 Case No. 03 of 2022
Damodar Valley Corporation (DVC)
Petition purported to be filed under Regulations 6.29 of the JSERC (Terms and Conditions for Determination of Distribution Tariff) Regulations, 2020 and its amendments thereof for approval of Power Purchase Agreement (PPA) between Damodar Valley Corporation (DVC) and Jyotikiran Energy Mumbai Pvt. Ltd. (JEM) for purchase of power by DVC from the solar photovoltaic power plant of 1137 kWp (Project 1 : 493.12kWp, Project 2: 446.9 kWp and Project 3: 196.98 kWp) to be commissioned at Koderma Thermal Power Station (KTPS) of DVC at Koderma district in the State of Jharkhand. 18.10.2022
1496 Case No.02 of 2022
Damodar Valley Corporation (DVC)
Petition purported to be filed under Regulations 6.29 of the JSERC (Terms and Conditions for Determination of Distribution Tariff) Regulations, 2020 and its amendments thereof for approval of Power Purchase Agreement (PPA) between Damodar Valley Corporation (DVC) and Jyotikiran Energy Mumbai Pvt. Ltd. (JEM) for purchase of power by DVC from the solar photovoltaic power plant of 278.72 kWp to be commissioned at Maithon of DVC Maithon, P.O. – Maithon Dam at Dhanbad District in the State of Jharkhand. 18.10.2022
1495 Miscellaneous Petition No. 02 of 2020
Jharkhand Bijli Vitran Nigam Limted
Order on MP No. 02 of 2020 18.10.2022
1494 Case No. 25 of 2020